The COVID-19 pandemic has interrupted the development of Norway’s offshore oil and gas projects, pushing up costs and postponing startups, the government and oil company Equinor said Oct. 7.
The costs of ongoing projects rose by 13.2 billion Norwegian crowns ($1.4 billion) from a year ago on an inflation-adjusted basis, government documents showed, as COVID-19 restrictions stalled construction at several fields.
“The COVID-19 pandemic and weakened Norwegian (currency) have negatively impacted some of the projects, but the combined project portfolio is still very resilient,” Equinor said in a separate statement.
Following the delays, Norway’s oil output for next year is now expected to be 2.15 million barrels per day, slightly less than the 2.24 million predicted for 2021 one year ago, the government’s budget showed.
Gas production is expected to be 117 billion cubic meters (Bcm), less than 121 Bcm forecast a year ago.
Equinor’s Martin Linge oil and gas field is now expected to cost 60.8 billion crowns, up from an estimate of 56.1 billion a year ago, Norway’s 2021 fiscal budget showed.
The company’s Johan Castberg Arctic oil field, meanwhile, is now expected to cost 53.4 billion crowns, up from 49 billion crowns previously, the government said.
Cost overruns also hit Equinor’s Njord Future, Repsol’s Yme and other developments.
In March, the long-delayed Martin Linge development became the first offshore field to be hit by the pandemic when installation work was halted after an employee tested positive for the virus.
Half of the inflation-adjusted cost increase of 3.6 billion crowns for Martin Linge was down to infection control measures, Equinor said.
The pandemic also interrupted construction of the Johan Castberg’s FPSO unit at a yard in Singapore, while the company also discovered technical problems.
Both projects have been delayed by about a year, with Martin Linge now expected to come on stream in the summer of 2021 and Johan Castberg in the fourth quarter of 2023.
The cost of the Njord Future project, which aims to produce an extra 175 million barrels of oil equivalent from Njord, and its tie-back Hyme also rose. The planned startup date has been delayed until next year.
As a result, several smaller projects, which are planning to use the Njord’s production facilities, such as Neptune Energy’s Fenja, will also be delayed.
Recommended Reading
US Expected to Supply 30% of LNG Demand by 2030
2024-02-23 - Shell expects the U.S. to meet around 30% of total global LNG demand by 2030, although reliance on four key basins could create midstream constraints, the energy giant revealed in its “Shell LNG Outlook 2024.”
API Gulf Coast Head Touts Global Emissions Benefits of US LNG
2024-04-01 - The U.S. and Louisiana have the ability to change global emissions through the export of LNG, although new applications have been frozen by the Biden administration.
CERAWeek: Two Minutes with EQT’s Toby Rice on Energy Security
2024-03-22 - EQT Corp. President and CEO Toby Z. Rice spoke to Hart Energy on March 20 on the sidelines of CERAWeek by S&P Global to discuss natural gas infrastructure bottlenecks, energy security and the company’s advances on LNG.
CERAWeek: JERA CEO Touts Importance of US LNG Supply
2024-03-22 - JERA Co. Global CEO Yukio Kani said during CERAWeek by S&P Global that it was important to have a portfolio of diversified LNG supply sources, especially from the U.S.
CERAWeek: Trinidad Energy Minister on LNG Restructuring, Venezuelan Gas Supply
2024-03-28 - Stuart Young, Trinidad and Tobago’s Minister of Energy, discussed with Hart Energy at CERAWeek by S&P Global, the restructuring of Atlantic LNG, the geopolitical noise around inking deals with U.S.-sanctioned Venezuela and plans to source gas from Venezuela and Suriname.