WASHINGTON—A federal judge in Montana on Aug. 15 ordered the U.S. State Department to do a full environmental review of a revised route for the Keystone XL crude oil pipeline, a move that could delay the project and prove a setback for the Trump administration.
For more than a decade, environmentalists, tribal groups, and ranchers have fought the $8-billion, 1,180-mile pipeline to carry heavy crude to Steele City in Nebraska from Canada’s oil sands in Alberta.
U.S. District Court Judge Brian Morris ruled for the Indigenous Environmental Network and other plaintiffs, ordering the review of a revised pipeline route through Nebraska to supplement one the department did on the original path in 2014.
In his ruling, Morris said the State Department was obligated to “analyze new information relevant to the environmental impacts of its decision” to issue a permit for the pipeline last year.
Supporting the project are Canadian oil producers, who face price discounts over transport bottlenecks, and U.S. oil interests and pipeline builders.
TransCanada Corp. (NYSE: TRP), which wants to build Keystone XL, did not immediately respond to a request for comment on the ruling. It hopes to start preliminary work in Montana in coming months and begin construction in the second quarter of 2019.
The White House did not immediately respond to a request for comment, nor did the State Department.
The ruling was “a rejection of the Trump administration’s attempt to flout the law and force Keystone XL on the American people,” said Jackie Prange, a lawyer for the Natural Resources Defense Council, an environmental group.
In 2015, then President Barack Obama, a Democrat, rejected the pipeline, saying it would add to emissions that cause climate change and would mostly benefit Canadians.
President Donald Trump, a Republican, pushed to approve the pipeline soon after he took office. A State Department official signed a so-called presidential permit in 2017 allowing the line to move forward.
However, Morris declined the plaintiff’s request to vacate that permit, which was based on the 2014 review.
Last year, Nebraska regulators approved an alternative route for the pipeline which will cost TransCanada millions of dollars more than the original path.
In a draft environmental assessment last month, the State Department said Keystone XL would cause no major harm to water supplies or wildlife. That review is less wide-ranging than the full environmental impact statement Morris ordered.
Recommended Reading
Eni Reports Discovery Offshore Mexico in Block 9
2024-07-10 - Italian energy giant Eni SpA announced a discovery at the Yopaat-1 EXP exploration well in the offshore Mexico Block 9 of the Cuenca Salina in the Sureste Basin, which potential up to 400 MMboe in place.
E&P Highlights: July 10, 2024
2024-07-10 - Here’s a roundup of the latest E&P headlines including TotalEnergies exiting South Africa to focus on opportunities in Namibia.
CNOOC’s Bohai Bay Well Achieves High Yield
2024-07-11 - CNOOC’s Bozhong 19-6 Condensate Gas Field D1 well, the first ultra-deep well in China’s Bohai Bay, is currently producing approximately 6,300 boe/d.
Goodbye Manual Control: Vital Energy’s Automation Program Boosts Production
2024-07-12 - Production, ESP efficiency soared when the company automated decisions with AI at the edge.
Southeast Asia NatGas Projects Could Unlock $100B Boom- Rystad
2024-07-17 - Southeast Asia's offshore gas industry is set for a $100 billion boom by 2028, driven by a flurry of final investment decisions by oil and gas majors and national oil companies, according to Rystad Energy.