The platform for the TotalEnergies-operated Fénix development has been installed offshore Argentina in 70 m of water, partner Wintershall Dea announced Feb. 13.
First gas from the development about 60 km off the coast of Tierra del Fuego is expected in November 2024 and to produce for more than 15 years, according to Wintershall Dea.
The installation of the 4,800-ton platform was carried out in two phases. In January, the jacket was installed with four piles, followed by the lift and setting of the 1,500-ton deck topsides module.
Four vessels were involved in the installation of both parts of the platform, led by Heerema’s heavy lift vessel Aegir.
The deck was transported from the Rosetti Marino shipyard in Italy to Tierra del Fuego onboard the heavy transport ship HTV Interocean II.
The Fénix platform’s 2,500-sq-m deck consists of five levels: the helipad, the upper deck, the main deck with the wellheads and instrument room and the lower deck. The platform is designed to be operated from shore without the need for a permanent crew.
“With the installation of the platform we have completed the surface facilities part of the Fénix development project within the targeted schedule,” Mariano Cancelo, vice president of production and development at Wintershall Dea in Argentina, said in a press release. “Our focus will now switch to the next step, which is the drilling of three production wells.”
A jackup rig will be temporarily located next to the Fénix platform to drill the wells.
Fénix is part of the world’s southernmost gas production concession, CMA-1.
TotalEnergies sanctioned the $706-million development in September 2022, expecting it will produce 10 MMcm/d of natural gas.
TotalEnergies operates the field with 37.5% interest on behalf of partners Wintershall Dea with 37.5% and Pan American Energy with 25%.
Recommended Reading
Oceaneering Won $200MM in Manufactured Products Contracts in Q4 2023
2024-02-05 - The revenues from Oceaneering International’s manufactured products contracts range in value from less than $10 million to greater than $100 million.
E&P Highlights: Feb. 5, 2024
2024-02-05 - Here’s a roundup of the latest E&P headlines, including an update on Enauta’s Atlanta Phase 1 project.
CNOOC’s Suizhong 36-1/Luda 5-2 Starts Production Offshore China
2024-02-05 - CNOOC plans 118 development wells in the shallow water project in the Bohai Sea — the largest secondary development and adjustment project offshore China.
TotalEnergies Starts Production at Akpo West Offshore Nigeria
2024-02-07 - Subsea tieback expected to add 14,000 bbl/d of condensate by mid-year, and up to 4 MMcm/d of gas by 2028.
US Drillers Add Oil, Gas Rigs for Third Time in Four Weeks
2024-02-09 - Despite this week's rig increase, Baker Hughes said the total count was still down 138 rigs, or 18%, below this time last year.