A federal judge ordered the U.S. Army Corps of Engineers to reconsider its environmental review of the Dakota Access Pipeline on June 14, opening up the possibility that the line could be shut at a later date.
U.S. District Judge James Boasberg in Washington said the Army Corps did not adequately consider the effects of a possible oil spill on the fishing and hunting rights of the Standing Rock Sioux tribe.
Operations of Energy Transfer Partners LP's (NYSE: ETP) pipeline have not been suspended but that could be considered at a later date, the order said. The $3.8 billion line began interstate crude oil delivery in May.
The parties are expected to meet Boasberg next June 21 to discuss future steps. The Standing Rock Sioux are expected to argue that pipeline operations should be halted.
The judge said in a 91-page decision that, while the Army Corps substantially complied with the National Environmental Policy Act, federal permits issued for the pipeline violated the law in some respects, saying in a court order the Corps did not "adequately consider the impacts of an oil spill on fishing rights, hunting rights, or environmental justice."
"To remedy those violations, the Corps will have to reconsider those sections of its environmental analysis upon remand by the Court," the judge said.
The tribe had sued the Army Corps over its approval of the controversial Dakota Access Pipeline in North Dakota, arguing the line could contaminate their water source, the Missouri River.
"We applaud the courts for protecting our laws and regulations from undue political influence and will ask the Court to shut down pipeline operations immediately,” Standing Rock Sioux Chairman Dave Archambault said in a statement.
It was unclear whether the judge would agree that the line should be shut. Independent research firm Clearview Energy Partners of Washington D.C. noted in a comment late on June 14 that Judge Boasberg's order pointed to "omissions" in the Corps' analysis, which the Corps may be able to address quickly, rather than larger errors that might require more study.
"We think that the Corps may be able to persuade the court to allow Dakota Access to continue operating while the omissions are addressed and the court reviews them for adequacy," they wrote.
Energy Transfer was not immediately available for comment.
In February, the Army Corps of Engineers granted the final easement needed to finish the controversial pipeline, which had been delayed for several months after protests led by the Standing Rock Sioux tribe and climate activists.
RELATED: Analysts: DAPL Conflict Hints At Troubles To Come
The controversial pipeline needed a final permit to tunnel under Lake Oahe, a reservoir that is part of the Missouri River.
Two previous arguments by the Standing Rock tribe—that the construction had threatened sacred sites, and that the presence of oil in the pipeline would damage sacred waters, had been rejected by the court.
President Donald Trump issued an executive order days after being sworn in directing the Army Corps to smooth the path to finishing the line, prompting complaints by the tribe and environmental groups that it had not done an adequate environmental review.
Recommended Reading
Going with the Flow: Universities, Operators Team on Flow Assurance Research
2024-03-05 - From Icy Waterfloods to Gas Lift Slugs, operators and researchers at Texas Tech University and the Colorado School of Mines are finding ways to optimize flow assurance, reduce costs and improve wells.
Axis Energy Deploys Fully Electric Well Service Rig
2024-03-13 - Axis Energy Services’ EPIC RIG has the ability to run on grid power for reduced emissions and increased fuel flexibility.
Defeating the ‘Four Horsemen’ of Flow Assurance
2024-04-18 - Service companies combine processes and techniques to mitigate the impact of paraffin, asphaltenes, hydrates and scale on production—and keep the cash flowing.
TGS Commences Multiclient 3D Seismic Project Offshore Malaysia
2024-04-03 - TGS said the Ramform Sovereign survey vessel was dispatched to the Penyu Basin in March.