U.S. energy regulators on July 15 granted Delfin LNG a second one-year extension until September 2021 to complete its proposed floating LNG export facility off the coast of Louisiana.
The U.S. Federal Energy Regulatory Commission in September 2017 authorized Delfin to build its project by September 2019.
The company in June 2019 asked FERC for a 3-1/2-year extension, but the agency only gave it one more year until September 2020 to finish the project.
Since Delfin still has not started building the facility, it asked the FERC in June for a second one-year extension, which the agency approved on July 15.
Officials at Delfin were not immediately available for comment.
Delfin’s project seeks to use existing offshore pipelines to supply gas to up to four vessels that could produce up to 13 million tonnes per annum (MTPA) of LNG or 1.7 billion cubic feet per day (Bcf/d) of natural gas.
In the past, the company said it planned to make a final investment decision (FID) to build the facility in 2020, which should enable it to enter service in mid-2024.
Like most other North American LNG developers, Delfin delayed making an FID from 2019 to 2020 as buyers became hesitant to sign long-term agreements needed to finance the billion-dollar projects because global gas prices collapsed due to an oversupplied market and coronavirus demand destruction.
In mid-2019, a dozen North American developers planned to make FIDs by the end of the year. None of those projects are under construction and all were delayed until 2020 or later.
At the start of this year, 12 companies said they planned to make FIDs in 2020. That total is now down to just four, and analysts said they expect only one of those projects to actually go forward this year.
Recommended Reading
Exxon’s Payara Hits 220,000 bbl/d Ceiling in Just Three Months
2024-02-05 - ExxonMobil Corp.’s third development offshore Guyana in the Stabroek Block — the Payara project— reached its nameplate production capacity of 220,000 bbl/d in January 2024, less than three months after commencing production and ahead of schedule.
What's Affecting Oil Prices This Week? (Feb. 5, 2024)
2024-02-05 - Stratas Advisors says the U.S.’ response (so far) to the recent attack on U.S. troops has been measured without direct confrontation of Iran, which reduces the possibility of oil flows being disrupted.
Tinker Associates CEO on Why US Won’t Lead on Oil, Gas
2024-02-13 - The U.S. will not lead crude oil and natural gas production as the shale curve flattens, Tinker Energy Associates CEO Scott Tinker told Hart Energy on the sidelines of NAPE in Houston.
What's Affecting Oil Prices This Week? (March 18, 2024)
2024-03-18 - On average, Stratas Advisors predicts that supply will be at a deficit of 840,000 bbl/d during 2024.
What's Affecting Oil Prices This Week? (March 11, 2024)
2024-03-11 - Stratas Advisors expects oil prices to move higher in the middle of the year, but for the upcoming week, there is no impetus for prices to raise.