McDermott International Inc. (MDR) has been awarded a brownfield project by Qatar Petroleum for the engineering, procurement, construction and installation (EPCI) of four wellhead jackets.
Installation of two jackets in the Bul-Hanine Field offshore east of Doha has been scheduled to be completed by December 2016 with the remaining two scheduled for completion in July 2017. The total weight of all four structures combined is 3,495 tons.
Revenue for the order will be included in McDermott’s third quarter 2015 backlog.
Detailed design engineering and procurement is expected to be performed by McDermott’s teams in Dubai, U.A.E. Jackets are scheduled for fabrication by McDermott’s Dubai, U.A.E.-based fabrication facility. Vessels from the McDermott global fleet are scheduled to undertake the installation work.
Recommended Reading
CorEnergy Infrastructure to Reorganize in Pre-packaged Bankruptcy
2024-02-26 - CorEnergy, coming off a January sale of its MoGas and Omega pipeline and gathering systems, filed for bankruptcy protect after reaching an agreement with most of its debtors.
Enbridge Advances Expansion of Permian’s Gray Oak Pipeline
2024-02-13 - In its fourth-quarter earnings call, Enbridge also said the Mainline pipeline system tolling agreement is awaiting regulatory approval from a Canadian regulatory agency.
Canadian Natural Resources Boosting Production in Oil Sands
2024-03-04 - Canadian Natural Resources will increase its quarterly dividend following record production volumes in the quarter.
Bobby Tudor on Capital Access and Oil, Gas Participation in the Energy Transition
2024-04-05 - Bobby Tudor, the founder and CEO of Artemis Energy Partners, says while public companies are generating cash, private equity firms in the upstream business are facing more difficulties raising new funds, in this Hart Energy Exclusive interview.
Genesis Energy Declares Quarterly Dividend
2024-04-11 - Genesis Energy declared a quarterly distribution for the quarter ended March 31 for both common and preferred units.