Equitrans Midstream Corp. said on Oct. 12 it will evaluate the cost and timing of the completion of the Mountain Valley natural gas pipeline based on ongoing litigation and upcoming federal approvals.
The U.S. Federal Energy Regulatory Commission (FERC) gave Mountain Valley permission late Oct. 9 to resume some construction on its $5.4 billion-$5.7 billion pipeline, which runs from Virginia to West Virginia.
“As the litigation process progresses and as we receive additional information from FERC regarding potentially releasing the remainder of the route for construction, (Mountain Valley) will continue to evaluate its current construction plans, budget and schedule,” Equitrans said.
Mountain Valley is one of several U.S. oil and gas pipelines delayed by regulatory and legal fights with environmental and local groups that found problems with federal permits issued by the Trump administration.
FERC suspended work on Mountain Valley a year ago due to litigation over the project’s Biological Opinion from the U.S. Fish and Wildlife Service (FWS), which allows construction in areas inhabited by endangered and threatened species.
The FWS issued a new Biological Opinion in early September. Environmental and other groups continue to challenge the latest FWS approval and other federal permits in court.
Analysts at Height Capital Markets said they expect the project to enter service in mid-2021 but noted timing could slip to third-quarter 2021 if legal challenges prevent some stream crossings.
“We acknowledge the legal challenge that is currently before Fourth Circuit Court of Appeals and have agreed to temporarily delay stream and waterbody activities out of respect for that process,” Equitrans said.
Equitrans has said it expects the pipeline, which is about 92% complete, to enter service in early 2021.
In February 2018, when Equitrans started construction, it estimated Mountain Valley would cost about $3.5 billion and be completed by the end of 2018.
Recommended Reading
Berry Announces Jeff Magids as New CFO
2025-01-21 - Jeff Magids was appointed as Berry Corp.’s new CFO on Jan. 21 in replacement of Mike Helm, effective immediately.
Talos Energy Zeroing in on New Skipper After Interim CEO Quits
2025-01-06 - Talos Energy said it has identified a finalist candidate to serve as the company’s permanent CEO starting end of first-quarter 2025.
Artificial Lift Firm Flowco’s Stock Surges 23% in First-Day Trading
2025-01-22 - Shares for artificial lift specialist Flowco Holdings spiked 23% in their first day of trading. Flowco CEO Joe Bob Edwards told Hart Energy that the durability of artificial lift and production optimization stands out in the OFS space.
SM Energy Adds Petroleum Engineer Ashwin Venkatraman to Board
2024-12-04 - SM Energy Co. has appointed Ashwin Venkatraman to its board of directors as an independent director and member of the audit committee.
Baker Hughes Wins Contracts for Woodside’s Louisiana LNG Project
2024-12-30 - Bechtel has ordered gas technology equipment from Baker Hughes for the first phase of Woodside Energy Group’s Louisiana LNG development.