The state of Western Australia has ordered an inquiry into a delay in burying carbon dioxide emissions at Chevron Corp.’s (NYSE: CVX) Gorgon LNG project, which could lead to a change in conditions on the project, on May 10.
The state approved the $54 billion Gorgon project in 2009 on the condition that at least 80% of carbon dioxide released in its gas processing operations over a five-year rolling average period would be buried.
“It has become apparent there needs to be a clearly defined start point for the commencement of the five-year rolling average,” Stephen Dawson, the state environment minister, told reporters in the Perth, the state capital, on May 7, according to an email sent to Reuters by his spokeswoman.
He ordered the state’s Environmental Protection Authority to report back within the next nine months whether the conditions should be changed, along with any other recommendations.
Chevron said it welcomed the review “to clarify the existing condition” on the carbon capture project.
“Our focus is on the safe commissioning and start-up of the carbon dioxide injection project and achieving a high percentage of injection over the 40-year life of the Gorgon project,” a Chevron spokeswoman said in emailed comments.
Chevron told the government last December it would not be able to start capturing and burying carbon dioxide until the fourth-quarter of 2018 at the earliest, after having found problems with valves and pipeline equipment during commissioning of its AU$2.5 billion (US$1.9 billion) injection system.
The Gorgon carbon dioxide injection system is the world’s largest capture and storage project.
Processing operations began in March 2016, when Gorgon started producing gas from the Jansz field.
However, Chevron only intended to start burying carbon dioxide after it started producing from the Gorgon field, which has a higher carbon dioxide content. Production started there in 2017.
Gorgon LNG is owned by Chevron, ExxonMobil Corp. (NYSE: XOM), Royal Dutch Shell (NYSE: RDS.A), and Japan’s Osaka Gas, Tokyo Gas and JERA.
Recommended Reading
SEC Adopts Climate Disclosure Rules in 3-2 Vote
2024-03-06 - The regulation requires companies to disclose Scope 1 and 2 emissions, weather-related risks and other climate-related data that could have a material business impact.
Majority of Recent CO2 Emissions Linked to 57 Producers - Report
2024-04-03 - The world's top three CO2-emitting companies in the period were state-owned oil firm Saudi Aramco, Russia's state-owned energy giant Gazprom and state-owned producer Coal India, the report said.
SAF End-users, Producers Talk Challenges, Solutions
2024-02-07 - The lower lifecycle emissions of sustainable aviation fuel are seen as a key lever for airlines to reduce carbon emissions, but cost is a challenge.
Coalition Launches Decarbonization Program in Major US Cities, Counties
2024-04-11 - A national coalition will start decarbonization efforts in nine U.S. cities and counties following a federal award of $20 billion “green bank” grants.
A Different Way to Approach Energy Industry Hiring
2024-02-07 - Modern energy companies have embraced competitive efficiency, cutting-edge innovation and ESG transparency. It is time for modern energy hiring to do the same.