Cheniere Energy Inc. said on Nov. 1 it expects to reach substantial completion of the third liquefaction train at its Corpus Christi LNG export plant in Texas earlier than previously expected in the first half of 2021.
Earlier, the company said it expected to complete the train in the second half of 2021. This would continue a pattern for Cheniere and Bechtel, the engineering firm building the trains, of completing units ahead of schedule and on budget.
Cheniere also said in its third-quarter earnings that it expects to complete the sixth train at its Sabine Pass LNG export plant in Louisiana in the first half of 2023.
The company said Corpus 3 was about 68.6% complete and Sabine 6 was about 38.1% complete.
Cheniere has five liquefaction trains operating at Sabine and two at Corpus.
Each train is capable of liquefying about 0.7 billion cubic feet per day (Bcf/d) of gas. One billion cubic feet is enough to supply about five million U.S. homes for a day.
In addition, the company is developing seven midscale LNG export trains at Corpus, called Stage 3, with a total capacity to liquefy about 1.25 Bcf/d of gas.
Cheniere CEO Jack Fusco told analysts the company plans to make a final investment decision to build Corpus Stage 3 in the first half of 2020. The company has said that would allow the plant to enter service in 2023.
Sabine was the first big LNG export facility to enter service in the Lower 48 U.S. states. When Sabine shipped its first cargo in February 2016, the U.S. was not exporting any LNG.
Since then, the country has become the fourth-biggest exporter of the fuel in the world in 2018, behind Qatar, Australia and Malaysia, and is on track to overtake Malaysia and become the third-biggest in 2019 and the biggest in the world in 2024.
Looking at terminals under construction, total U.S. LNG export capacity is expected to rise to 6.9 bcfd by the end of 2019 and 9.6 bcfd in 2020 from 6.8 bcfd now.
Cheniere has estimated the cost of the first five trains at Sabine, including financing, at between $17.5 billion and $18.5 billion, while the first three trains at Corpus are expected to cost between $15 billion and $16 billion after financing.
Cheniere said it has a $2.5 billion contract with Bechtel to build Sabine 6.
Recommended Reading
Gulfport Plans Liquids-rich Program After ‘Strong’ Ohio Oil Tests
2024-05-01 - Appalachia gas producer Gulfport Energy continues to report “strong oil production” from a two-well Hendershot pad drilled in eastern Ohio last year. Gulfport plans to develop additional liquids-rich opportunities this year as natural gas prices hover near record lows.
Chevron CEO: Permian, D-J Basin Production Fuels US Output Growth
2024-04-29 - Chevron continues to prioritize Permian Basin investment for new production and is seeing D-J Basin growth after closing its $6.3 billion acquisition of PDC Energy last year, CEO Mike Wirth said.
Novo II Reloads, Aims for Delaware Deals After $1.5B Exit Last Year
2024-04-24 - After Novo I sold its Delaware Basin position for $1.5 billion last year, Novo Oil & Gas II is reloading with EnCap backing and aiming for more Delaware deals.
Enverus: 1Q Upstream Deals Hit $51B, but Consolidation is Slowing
2024-04-23 - Oil and gas dealmaking continued at a high clip in the first quarter, especially in the Permian Basin. But a thinning list of potential takeout targets, and an invigorated Federal Trade Commission, are chilling the red-hot M&A market.