BP on Oct. 22 confirmed it has received approval from the Oil and Gas Authority (OGA) to proceed with the Alligin development west of Shetland, which will target 20 million barrels of oil equivalent (MMboe), and is expected to produce 12,000 barrels gross of oil equivalent a day at peak.
Alligin is located 140 km west of Shetland in a water depth of 475 m. It forms part of the Greater Schiehallion Area.
The Alligin development will consist of two wells, which will be tied-back into the existing Schiehallion and Loyal subsea infrastructure, utilizing the processing and export facilities of the Glen Lyon floating, production storage, offload (FPSO) vessel. It is expected to come on stream in 2020.
The development will include new subsea infrastructure, consisting of gas lift and water injection pipeline systems, and a new controls umbilical. The wells will be drilled by the Deepsea Aberdeen rig.
Alligin (BP 50% operator; Shell 50%) is part of a series of infrastructure-led subsea tie-back developments in the North Sea, accessing new production from fields located near to established producing infrastructure.
This is BP’s second North Sea development approval in the past two months. Vorlich, which targets 30 MMboe, received regulatory approval in September. BP’s Clair Ridge development is expected to start-up later this year. It is expected to target 640 MMbbl of resources and have a peak production of 120,000 bbl/d.
BP also has 32% stake in the North Sea Culzean development, which is expected to supply around 5% of UK gas requirements. First gas is anticipated in 2019.
Earlier this year, BP was awarded seven licenses, five as operator and two as partner, in the North Sea’s 30th Offshore Licensing Round. And in January, BP announced two new discoveries in the North Sea at Capercaillie in the Central North Sea and Achmelvich west of Shetland.
Recommended Reading
Oceaneering Won $200MM in Manufactured Products Contracts in Q4 2023
2024-02-05 - The revenues from Oceaneering International’s manufactured products contracts range in value from less than $10 million to greater than $100 million.
E&P Highlights: Feb. 5, 2024
2024-02-05 - Here’s a roundup of the latest E&P headlines, including an update on Enauta’s Atlanta Phase 1 project.
CNOOC’s Suizhong 36-1/Luda 5-2 Starts Production Offshore China
2024-02-05 - CNOOC plans 118 development wells in the shallow water project in the Bohai Sea — the largest secondary development and adjustment project offshore China.
TotalEnergies Starts Production at Akpo West Offshore Nigeria
2024-02-07 - Subsea tieback expected to add 14,000 bbl/d of condensate by mid-year, and up to 4 MMcm/d of gas by 2028.
US Drillers Add Oil, Gas Rigs for Third Time in Four Weeks
2024-02-09 - Despite this week's rig increase, Baker Hughes said the total count was still down 138 rigs, or 18%, below this time last year.