At the Ebok Field in Nigeria, Afren and its partner Oriental Energy Resources Ltd. have installed the jacket for the Ebok Central Fault Block Extension (CFBx) platform, according to a press release.

The installation of the decks and bridge will be completed in early January 2015 once the wellhead jacket at Okwok has been installed, following which the partners will commence the hookup and commissioning of the CFBx platform.

The work program at the CFBx will include up to nine new wells to be drilled and brought onstream by the end of 2015 targeting both producing and undeveloped reservoirs. Elsewhere at the North Fault Block, the partners continue to make progress and are targeting completion of the third new producer by mid-December 2014. The forward program at the North Fault Block will incorporate up to an additional five wells by year-end 2015.