First gas from the development about 60 km off the coast of Tierra del Fuego is expected in November 2024 and to produce for more than 15 years. (Source: TotalEnergies Austral)
The platform for the TotalEnergies-operated Fénix development has been installed offshore Argentina in 70 m of water, partner Wintershall Dea announced Feb. 13.
First gas from the development about 60 km off the coast of Tierra del Fuego is expected in November 2024 and to produce for more than 15 years, according to Wintershall Dea.
The installation of the 4,800-ton platform was carried out in two phases. In January, the jacket was installed with four piles, followed by the lift and setting of the 1,500-ton deck topsides module.
Four vessels were involved in the installation of both parts of the platform, led by Heerema’s heavy lift vessel Aegir.
The deck was transported from the Rosetti Marino shipyard in Italy to Tierra del Fuego onboard the heavy transport ship HTV Interocean II.
The Fénix platform’s 2,500-sq-m deck consists of five levels: the helipad, the upper deck, the main deck with the wellheads and instrument room and the lower deck. The platform is designed to be operated from shore without the need for a permanent crew.
“With the installation of the platform we have completed the surface facilities part of the Fénix development project within the targeted schedule,” Mariano Cancelo, vice president of production and development at Wintershall Dea in Argentina, said in a press release. “Our focus will now switch to the next step, which is the drilling of three production wells.”
A jackup rig will be temporarily located next to the Fénix platform to drill the wells.
Fénix is part of the world’s southernmost gas production concession, CMA-1.
TotalEnergies sanctioned the $706-million development in September 2022, expecting it will produce 10 MMcm/d of natural gas.
TotalEnergies operates the field with 37.5% interest on behalf of partners Wintershall Dea with 37.5% and Pan American Energy with 25%.
Recommended Reading
The Wall: Uinta, Green River Gas Fills West Coast Supply Gaps
2025-03-05 - Gas demand is rising in the western U.S., and Uinta and Green River producers have ample supply and takeaway capacity.
Intensity Infrastructure Partners Pitches Open Season for Bakken NatGas Egress
2025-02-04 - Analysts note the Bakken Shale’s need for more takeaway capacity as Intensity Infrastructure Partners launches an open season for a potential 126-mile natural gas transport line out of the basin.
Apollo Acquires BP’s Gas Pipeline Stake for $1B
2025-03-23 - BP Pipelines holds a 12% interest in the Trans-Anatolian Natural Gas Pipeline (TANAP), which transports natural gas from Azerbaijan across Turkey.
East Daley: Midstream Investors Drawn to Southeast as Demand Heats Up
2025-03-25 - Competition for gas supply will heat up as demand from data centers and new LNG projects jockey for a spot on takeaway lines.
Williams Commissions Two NatGas Projects to Expand Transco Network
2025-04-01 - Midstream company Williams Cos. added to its network capacity in the southern U.S. with the commissioning of the Southeast Energy Connector and the Texas to Louisiana Energy Pathway.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.