The first liquefied natural gas (LNG) tanker to berth at Shell's Prelude floating LNG site off Western Australia since it was shut down after a fire has begun loading, Refinitiv data shows.
The Methane Becki Anne vessel berthed at the Prelude plant on Jan. 17, Refinitiv ship-tracking data showed.
Gas production at the 3.6 million tonne Prelude facility had been suspended in mid-December after a small fire. At the time, Shell gave no timeline for when the plant would resume output but said the fire was much less serious than one that shut Prelude a year ago.
A Shell spokeswoman on Jan. 17 said there were no updates.
Prelude's floating LNG vessel, the world's largest, previously suffered a four-month shutdown because of a power failure in December 2021. Production was disrupted again in July last year by a workers strike, with output resuming in September.
Recommended Reading
E&P Highlights: Feb. 26, 2024
2024-02-26 - Here’s a roundup of the latest E&P headlines, including interest in some projects changing hands and new contract awards.
TotalEnergies Starts Production at Akpo West Offshore Nigeria
2024-02-07 - Subsea tieback expected to add 14,000 bbl/d of condensate by mid-year, and up to 4 MMcm/d of gas by 2028.
Well Logging Could Get a Makeover
2024-02-27 - Aramco’s KASHF robot, expected to deploy in 2025, will be able to operate in both vertical and horizontal segments of wellbores.
Shell Brings Deepwater Rydberg Subsea Tieback Onstream
2024-02-23 - The two-well Gulf of Mexico development will send 16,000 boe/d at peak rates to the Appomattox production semisubmersible.
Remotely Controlled Well Completion Carried Out at SNEPCo’s Bonga Field
2024-02-27 - Optime Subsea, which supplied the operation’s remotely operated controls system, says its technology reduces equipment from transportation lists and reduces operation time.