Refineria de Cartagena (Reficar), a refinery owned by Colombia's largest company Ecopetrol, is set to receive more than $1 billion following an arbitration ruling in its favor against a group of contractors.
The International Chamber of Commerce ordered contractor CB&I to pay more than $1 billion to Reficar, plus interest gains from Dec. 31, 2015, Ecopetrol, a majority state-owned oil company, said.
Reficar sought arbitration in March 2016 amid a dispute with consortium CB&I, made up of Contractor Chicago Bridge and Iron Company NV, CB&I (U.K.)and CBI Colombiana SA.
The unit accused the consortium of doubling construction costs during the renovation of the refinery and failings in the engineering, procurement and construction (EPC) contract.
"The unanimous decision of the arbitration tribunal confirmed contractor CB&I was responsible for breaching its obligations under the EPC contract," Ecopetrol said in a statement published late on June 7.
Furthermore, CB&I's claims for $400 million were dismissed, Ecopetrol added, and the consortium was ordered to settle the EPC contract, as requested by Reficar.
The decision by the tribunal may be subject to formal corrections and clarifications, the statement added.
Reficar began operating at the end of 2015 following two years of delays and an investment of over $8 billion, double the expected figure.
The refinery, in northern Colombia, can process up to 200,000 bbl/d and is second only to the refinery in Barrancabermeja, which can process up to 250,000 bbl/d.
Ecopetrol generates most of the country's oil production. It owns the two main refineries as well as most of the pipeline network.
Recommended Reading
TotalEnergies Starts Production at Akpo West Offshore Nigeria
2024-02-07 - Subsea tieback expected to add 14,000 bbl/d of condensate by mid-year, and up to 4 MMcm/d of gas by 2028.
Well Logging Could Get a Makeover
2024-02-27 - Aramco’s KASHF robot, expected to deploy in 2025, will be able to operate in both vertical and horizontal segments of wellbores.
Shell Brings Deepwater Rydberg Subsea Tieback Onstream
2024-02-23 - The two-well Gulf of Mexico development will send 16,000 boe/d at peak rates to the Appomattox production semisubmersible.
E&P Highlights: Feb. 26, 2024
2024-02-26 - Here’s a roundup of the latest E&P headlines, including interest in some projects changing hands and new contract awards.
Remotely Controlled Well Completion Carried Out at SNEPCo’s Bonga Field
2024-02-27 - Optime Subsea, which supplied the operation’s remotely operated controls system, says its technology reduces equipment from transportation lists and reduces operation time.