Conventional practices have focused on controlling sand in-situ using a variety of methods. Gravel packs in the 1970s and 1980s followed by frac packing in the 1990s were considered state-of-the-art solutions. Projections now show that half of future hydrocarbon production will come from reservoirs prone to sand production. Furthermore, the industry’s needs have evolved to more complex completions, requiring a concentration of new technologies and expertise.
According to the 2006 Spears report, overall sand management expenditures, including sand
Figure 1. Sand Management key influence roadmap. (All graphics courtesy of Schlumberger) |
Economic drivers include rising rig costs as well as the cost of deferred production. In addition, efficiency is paramount as completion time equals or exceeds drilling time. So any procedure with the potential to eliminate or delay future well interventions deserves industry attention. The evolution of innovative sand control techniques testifies to the complexity of the problem and the need to balance economics and productivity.
Engineering sand management
Predicting wells’ probability to produce sand hinges on many factors. Principal among these is rock mechanics, but the type of well and the way it is drilled, completed and produced also
Figure 2. Current market trends show increasing expenditures in openhole completions. |
Prevention is a fundamental component of sand management. This phase begins with implementation of designs indicated by the prediction phase. Solutions range from establishing and maintaining production parameters such as flow rate and drawdown that are below threshold levels for sand production to installing complex mechanical exclusion techniques. These include openhole gravel packs, standalone screens, cased-hole gravel and frac packs, screenless completions using fracturing with proppant control, or oriented perforating.
Sometimes a combination of techniques may be appropriate.
Real-time monitoring is necessary because reservoir conditions are subject to change over
Figure 3. Increase in deepwater completions represented by the number of subsea wellheads per year. |
If a well is already producing sand, or if sanding commences despite all efforts to prevent it, remediation treatments can be performed to correct the problem. These treatments can be implemented through tubing and include gravel packing, fracturing with proppant flowback control and installing a screenless completion.
Openhole solutions show promise
The evolution of drilling technologies has led to an increasing number of horizontal wells; and openhole completions are on the rise (Figure 2). This is linked to the exponential growth in deepwater and subsea developments (Figure 3), which require an extended completion planning cycle in excess of 3 to 5 years.
Another factor is the growing demand of reservoir pressure maintenance by water or gas injection. On the latest deepwater developments, the ratio has increased to one injector well
Figure 4. Typical openhole gravel pack completion and pumping treatment. |
A significant portion of the growth in openhole completions comes from gravel pack (Figure 4). Dedicated equipment such as openhole service tools, washpipe diverter valves and supporting chemistry such as a shale stabilizer and friction reducers have been developed to overcome the original limits and increase reliability of the existing gravel packing techniques. These new technologies complement the existing water pack and alternate path systems.
Openhole zonal isolation packers and inflow control devices, whose purpose is to equalize reservoir inflow across long horizontal screens to reduce water or gas coning, have been introduced to improve completion versatility and reservoir management.
A line in the sand
Schlumberger has considerable experience in all segments of sand management, and experience teaches us that no problem can be resolved in a vacuum. Recently, the company launched an initiative to develop a unique business line of Sand Management Services integrated with production optimization techniques and executed by a coordinated field team having deep experience in pressure pumping and completion services.
Worldwide sand management
The threat of sand production is felt worldwide, but there are too many variables — no single solution will do. By applying the principles of prediction, planning, prevention, monitoring and remediation we can resolve sand problems while optimizing production and extending the economic life of valuable assets.
Recommended Reading
Rystad: More Deepwater Wells to be Drilled in 2024
2024-02-29 - Upstream majors dive into deeper and frontier waters while exploration budgets for 2024 remain flat.
E&P Highlights: March 4, 2024
2024-03-04 - Here’s a roundup of the latest E&P headlines, including a reserves update and new contract awards.
TotalEnergies Starts Production at Akpo West Offshore Nigeria
2024-02-07 - Subsea tieback expected to add 14,000 bbl/d of condensate by mid-year, and up to 4 MMcm/d of gas by 2028.
Deepwater Roundup 2024: Offshore Africa
2024-04-02 - Offshore Africa, new projects are progressing, with a number of high-reserve offshore developments being planned in countries not typically known for deepwater activity, such as Phase 2 of the Baleine project on the Ivory Coast.
E&P Highlights: Feb. 26, 2024
2024-02-26 - Here’s a roundup of the latest E&P headlines, including interest in some projects changing hands and new contract awards.