Freeport LNG's long-idled LNG export plant in Texas was on track to receive no natural gas from pipelines on Feb. 7 after receiving small amounts over the past 12 days, Refinitiv Eikon data showed.
Since Jan. 26, when federal regulators approved the company's plan to start cooling some pipes, the plant has pulled in an average of 34 million cubic feet per day of pipeline gas.
That is a fraction of what it can pull in when operating at full power. Freeport can turn about 2.1 billion cubic feet of gas into LNG each day, which is about 2% of total U.S. daily gas production.
"We continue to progress our work towards the safe restart of our liquefaction facility," Freeport LNG spokesperson Heather Browne said in an email. The company had no comment on the gas flows to the plant.
Many analysts have said they do not expect the plant to return to full power until mid March or later. A couple of Freeport's customers - Japan's JERA and Osaka Gas - have said they do not expect to get LNG from the plant until after March.
Last week, Freeport told Texas regulators it would start sending gas to one of three liquefaction trains, which turn gas into LNG.
The plant, however, is waiting for permission from federal regulators to start loading LNG on ships to free up space in its storage tanks.
RELATED
Freeport LNG Seeks US Approval to Restart Loading at Texas Export Plant
Freeport, the second biggest U.S. LNG export plant, shut after a fire in June 2022.
The energy market expects gas prices to rise once the plant starts producing LNG again.
But gas futures were trading near a 25-month low mostly because mild weather this winter has kept heating demand for the fuel low.
Federal regulators will hold a public meeting on Freeport on Feb. 11 to provide members of the community and other interested parties an opportunity to voice concerns about Freeport's restart plans and to receive an update on what is happening at the plant.
Recommended Reading
E&P Highlights: Feb. 26, 2024
2024-02-26 - Here’s a roundup of the latest E&P headlines, including interest in some projects changing hands and new contract awards.
Exxon Mobil Green-lights $12.7B Whiptail Project Offshore Guyana
2024-04-12 - Exxon Mobil’s sixth development in the Stabroek Block will add 250,000 bbl/d capacity when it starts production in 2027.
Exxon Ups Mammoth Offshore Guyana Production by Another 100,000 bbl/d
2024-04-15 - Exxon Mobil, which took a final investment decision on its Whiptail development on April 12, now estimates its six offshore Guyana projects will average gross production of 1.3 MMbbl/d by 2027.
CEO: Continental Adds Midland Basin Acreage, Explores Woodford, Barnett
2024-04-11 - Continental Resources is adding leases in Midland and Ector counties, Texas, as the private E&P hunts for drilling locations to explore. Continental is also testing deeper Barnett and Woodford intervals across its Permian footprint, CEO Doug Lawler said in an exclusive interview.
For Sale, Again: Oily Northern Midland’s HighPeak Energy
2024-03-08 - The E&P is looking to hitch a ride on heated, renewed Permian Basin M&A.