A Minnesota judge on Oct. 16 ruled that the state’s pollution regulator and Enbridge Inc. used proper methods for water crossing for its Line 3 oil pipeline replacement, clearing another hurdle for the project that has faced years of delay.
Judge James LaFave upheld the draft water quality certificate that Minnesota Pollution Control Agency issued to Enbridge in February, quashing challenges by activist groups and Indigenous bands that had raised concerns regarding Enbridge’s intentions to protect streams and wetlands the pipeline crosses.
Line 3, built in the 1960s, carries less oil than it was designed for because of age and corrosion. Replacing it would allow the company to boost flow from an oil hub in Edmonton, Alberta, to Midwest refiners.
The report said the petitioners have failed to prove that the agency and Enbridge “undercounted the full acreage of wetlands that will be physically altered by trenching.”
A shortage of pipelines has weakened Canadian oil prices in recent years, but capacity became ample this year after deep oil production cuts during the COVID-19 pandemic.
Calgary, Alberta-based Enbridge said on Oct. 16 it continues to work with permitting agencies for the timely issuance of remaining permits in order for construction to start before year-end 2020.
Recommended Reading
G7 Reaches Deal to Exit from Coal by 2035
2024-04-29 - The accord will be included in the G7 energy ministers' final communique to be released on April 30.
OTC: Will More Electrical Demand Bring Energy Debate Back to Reality?
2024-05-06 - Energy experts, including Scott Tinker, touted the importance of discussing the environmental and economic impacts of moving energy forward at the 2024 Offshore Technology Conference.
Tangled Up in Blue: Few Developers Take FID on Hydrogen Projects
2024-04-03 - SLB, Linde and Energy Impact Partners discuss hydrogen’s future and the role natural gas will play in producing it.
Markman: Want CO2 Gone Now? Well, You Don’t Always Get What You Want
2024-04-29 - A slew of scenarios shows that climate goals can be achieved with the use of fossil fuels and CCUS.
Sinopec Completes Drilling of China’s Deepest Geothermal Well
2024-04-11 - Sinopec said the Fushen-1 Well was drilled to a depth of 5,200 meters.