Greece, Cyprus and Israel on Jan. 2 signed a deal to build a 1,900 km (1,180 mile) subsea pipeline to carry natural gas from the eastern Mediterranean's rapidly developing gas fields to Europe.
Although Turkey opposes the project, the countries aim to reach a final investment decision by 2022 and have the pipeline completed by 2025 to help Europe diversify its energy resources.
European governments and Israel last year agreed to proceed with the so-called EastMed project, a $6 billion to $7 billion pipeline project that is expected initially to carry 10 billion cubic meters of gas per year from Israeli and Cypriot waters to the Greek island of Crete, on to the Greek mainland and into Europe's gas network via Italy.
The energy ministers of Greece, Israel and Cyprus—Kostis Hatzidakis, Yuval Steinitz and Yiorgos Lakkotrypis—signed the final agreement on the pipeline at a ceremony in Athens.
Last month a Turkish official said there was no need to build the EastMed pipeline because the trans-Anatolian pipeline already existed.
Turkish Foreign Ministry spokesman Hami Aksoy said any project that ignored the rights of Turkey and Turkish Cypriots over natural resources in the eastern Mediterranean would fail.
"The most economical and secure route to utilize the natural resources in the eastern Mediterranean and deliver them to consumption markets in Europe, including our country, is Turkey," he said in a statement on Jan. 2.
Greek Prime Minister Kyriakos Mitsotakis, Cypriot President Nicos Anastasiades and Israeli Prime Minister Benjamin Netanyahu said the deal was not turning against any country.
"It [the agreement] ... supports a common aim for peace, security and stability in the particularly vulnerable region of the Eastern Mediterranean," Anastasiades said.
The region lacks significant oil and gas infrastructure and political relations between the countries—including Cyprus, Greece, Egypt, Israel, Lebanon and Syria—are strained on a number of fronts.
The signing of the EastMed pipeline comes weeks after Turkey and Libya struck an accord on sea boundaries in the Mediterranean, a move which Greece, Cyprus and Israel opposed.
Analysts say that pact could present a barrier to the proposed pipeline which would have to cross the planned Turkey-Libya economic zone.
"If Turkey would be interested, the door is open," Israel's Energy Minister Yuval Steinitz told Reuters.
"We are ready to discuss some kind of cooperation, energy cooperation, also with the Turks. We are not against the Turks but we are very much in favor of the EastMed gas pipeline project," he said.
The pipeline project is owned by IGI Poseidon, a joint venture between Greek gas firm DEPA and Italian energy group Edison.
DEPA on Jan. 2 signed a letter of intent with Energean, a gas producer with a focus on the Eastern Mediterranean, to buy two billion cubic meters of gas annually from Energean's gas fields off Israel via the planned pipeline.
Greece has said the agreement will be concluded once Italy signs off on it too.
Recommended Reading
Sangomar FPSO Arrives Offshore Senegal
2024-02-13 - Woodside’s Sangomar Field on track to start production in mid-2024.
NAPE: Chevron’s Chris Powers Talks Traditional Oil, Gas Role in CCUS
2024-02-12 - Policy, innovation and partnership are among the areas needed to help grow the emerging CCUS sector, a Chevron executive said.
CNOOC Makes 100 MMton Oilfield Discovery in Bohai Sea
2024-03-18 - CNOOC said the Qinhuangdao 27-3 oilfield has been tested to produce approximately 742 bbl/d of oil from a single well.
TPH: Lower 48 to Shed Rigs Through 3Q Before Gas Plays Rebound
2024-03-13 - TPH&Co. analysis shows the Permian Basin will lose rigs near term, but as activity in gassy plays ticks up later this year, the Permian may be headed towards muted activity into 2025.
Proven Volumes at Aramco’s Jafurah Field Jump on New Booking Approach
2024-02-27 - Aramco’s addition of 15 Tcf of gas and 2 Bbbl of condensate brings Jafurah’s proven reserves up to 229 Tcf of gas and 75 Bbbl of condensate.