PennEast Pipeline said on Aug.12 it still expects to complete the first phase of its $1.2 billion natural gas pipe in Pennsylvania in 2022 even though it put off acquiring rights of way for the project due to legal and regulatory hurdles.
PennEast, which seeks to complete the pipeline's second phase from Pennsylvania into New Jersey in 2023, is just one of several long-delayed projects facing opposition from Northeastern states as the region transitions from fossil fuels to cleaner forms of power, like wind and solar.
"Given the uncertainty on timing to resolve the remaining legal and regulatory hurdles, PennEast believes it is not prudent to complete the acquisition of the rights of way in the pending actions in Pennsylvania, as it might not be necessary for some time," PennEast said in a statement.
That "uncertainty" caused PennEast partner New Jersey Resources Corp last week to announce a $72.7 million after-tax impairment charge related to its investment in the project.
In June, the U.S. Supreme Court overturned a Third Circuit decision that blocked PennEast from using federal eminent domain rules to seize New Jersey state-owned or controlled land.
That victory cleared one hurdle, but more remain. In addition to completing the rights of way, PennEast still needs permits from environmental Pennsylvania and New Jersey regulators and others before it can start construction.
The U.S. Federal Energy Regulatory Commission (FERC) approved PennEast's request to build the pipeline in January 2018. The company had hoped to complete the project in 2019.
The 120-mile (193 kilometer) pipe is designed to deliver 1.1 billion cubic feet per day of gas from the Marcellus shale to customers in Pennsylvania and New Jersey.
PennEast partners include units of NJR, South Jersey Industries Inc, Southern Co, Enbridge Inc and UGI Corp.
Recommended Reading
Permian Resources Closes $820MM Bolt-on of Oxy’s Delaware Assets
2024-09-17 - The Permian Resources acquisition includes about 29,500 net acres, 9,900 net royalty acres and average production of 15,000 boe/d from Occidental Petroleum’s assets in Reeves County, Texas.
Crackin’ It at Kraken: Inside the Bakken’s Ramped-up Private E&P
2024-07-24 - Kayne Anderson-backed Kraken Resources is producing more than 80,000 boe/d today and has a new Fitch Ratings credit score to take to the M&A bank.
Kolibri Global Drills First Three SCOOP Wells in Tishomingo Field
2024-09-18 - Kolibri Global Energy reported drilling the three wells in an average 14 days, beating its estimated 20-day drilling schedule.
Private Equity Looks for Minerals Exit
2024-07-26 - Private equity firms have become adroit at finding the best mineral and royalties acreage; the trick is to get public markets to pay more attention.
Avant Natural Resources Steps Out with North Delaware Avalon Tests
2024-08-21 - With the core of the Delaware Basin in full manufacturing mode, Avant Natural Resources is pushing an operated portfolio into the northern reaches of the New Mexico Delaware.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.