When is a road a road? Or, is a road a road a road? To be a road, or not to be a road? That was the question.
In a federal court, the pipeline won. The “road” lost.
A federal court of appeals has issued a first ruling on Pres. Bill Clinton’s “Roadless Rule” involving a pipeline project—and the pipeline project has won—says Poe Leggette, attorney with Fulbright & Jaworski LLP. The appellate court has agreed with a district court’s denial of environmentalists’ claim that trucks moving in and out of an area in central Colorado to build a pipeline de facto create a road, thus the rule applies.
The case is Wilderness Workshop v. Bureau of Land Management, No. 08-1165.
“This is the first ruling by any federal court of appeals on the application of the ‘roadless rule’ to pipeline construction,” Leggette says. He reports a summary of the ruling in the firm’s monthly “Fulbright Western Lands & Energy Monthly Update” newsletter.
“The chief issue before the court was whether the project proponent’s use of motorized equipment to lay the pipeline made the pipeline right of way a ‘motor vehicle travelway,’ a term used in the ‘roadless rule’ to define what a ‘road’ is.”
The BLM and U.S. Forest Service were on the pipeline’s side in this case, saying vehicles along the pipeline route made that route a road merely for purposes of construction.
“The court reviewed the agencies’ position to see whether it was ‘plainly inconsistent’ with the text of the ‘roadless rule,’” he says.
The preamble of the ‘roadless rule’ in the federal legislation, though, says roadless areas are not the same as wilderness areas “and would remain open for many activities, including ‘motorized uses.’”
Leggette says, “The court also rejected the argument of the environmental organizations that the environmental-impact statement for the pipeline should have treated all future wells that could be connected to the pipeline as ‘connected actions’ under the National Environmental Policy Act.”
For more on this, Leggette can be reached at pleggette@fulbright.com.
–Nissa Darbonne, Executive Editor, Oil and Gas Investor, A&D Watch, OilandGasInvestor.com; ndarbonne@hartenergy.comRecommended Reading
Haynesville to Lead Gas Production Growth in 2023
2023-03-30 - Enverus expects the Haynesville to lead gas production growth in 2023 and then fall thereafter before growing again between 2025 and 2027, Bernadette Johnson, the firm’s general Manager, said at Hart Energy’s DUG Haynesville conference in Shreveport, Louisiana.
Southwestern’s Haynesville Chief on M&A, Gulf Coast Advantages and RSG [WATCH]
2023-03-30 - Andy Huggins, senior vice president of the Haynesville division at Southwestern Energy Co. discusses M&A, how the company’s Appalachia and Haynesville assets complement each other and efforts to certify its natural gas as responsibly sourced, particularly for utilities and end-users in Europe.
Public, Private E&Ps Split on Permian Basin Drilling Strategies
2023-03-29 - The Permian led the nation in drilling rig activity in the past year, with data showing much of that growth coming from large, public upstream operators as private companies such as CrownQuest Operating, Iskandia Energy and Mack Energy have downshifted.
McDermott Wins Manatee FEED
2023-03-28 - The Trinidad and Tobago Manatee field is planned to start production in 2027.
Electrifying the Permian: BPX Energy Touts Emissions Reductions in the Basin
2023-03-28 - BPX Energy’s electrification efforts in the Permian Basin and the installation of centralized handling facilities are part of the operator’s roadmap to net zero emissions.