Virginia Attorney General Mark Herring on Jan. 22 filed a brief in the Atlantic Coast natural gas pipeline case at the U.S. Supreme Court opposing construction of Dominion Energy Inc.'s $7.3 billion to $7.8 billion project.
Atlantic Coast, the nation's most expensive gas pipe, is one of several projects that have received federal permits in recent years but have been delayed by state opposition and local and environmental legal and regulatory battles.
In the Supreme Court case, Dominion and its partners, Duke Energy Corp. and Southern Co., said the U.S. Forest Service was correct in issuing Atlantic Coast a permit to cross the Appalachian Trail in Virginia.
In his brief, Herring asked the court to affirm the Fourth Circuit Court of Appeals ruling that invalidated the Forest Service permit.
"The Forest Service failed to conduct the meticulous review of Atlantic’s permit application called for by the Service’s governing statutes and regulations," Herring said, noting "the permitting process was rushed and slipshod and driven by Atlantic’s arbitrary deadlines."
Dominion spokesman Aaron Ruby said the company respectfully disagreed with the Attorney General, noting the Forest Service has the full authority to authorize the Appalachian Trail crossing.
The Supreme Court is scheduled to hear the case on Feb. 24.
Dominion has said it expects to complete Atlantic Coast in early 2022.
"Our region’s current infrastructure is not keeping up with growing demand for gas," Ruby said, noting communities in southeast Virginia and northeast North Carolina are experiencing chronic shortages of gas, forcing utilities to shut off service to major industries and the U.S. military during the winter.
Herring, however, questioned whether the project is needed, citing numerous sources that indicate gas demand is actually decreasing, and that renewable energies are becoming more cost competitive.
"The ever-rising costs of building [the pipeline] will be passed on to consumers, by the companies that have contracted with Atlantic to carry gas through the pipeline."
When Dominion started work on the 1.5 billion cubic feet per day pipe in the spring of 2018, the company estimated it would cost between $6 billion and $6.5 billion and be completed in late 2019.
In addition to the Appalachian Trail case, the Fourth Circuit also rejected a permit from the U.S. Fish and Wildlife Service (FWS), saying the agency's decisions were arbitrary and would jeopardize endangered species.
Dominion suspended construction of the 600-mile (966-km) project in December 2018 after the Fourth Circuit stayed an earlier FWS' permit.
Recommended Reading
New Permian Math: Vital Energy and 42 Horseshoe Wells
2024-05-10 - Vital Energy anticipates making 42 double-long, horseshoe-shaped wells where straight lines would have made 84 wells. The estimated savings: $140 million.
SM Energy Targets Prolific Dean in New Northern Midland Play
2024-05-09 - KeyBanc Capital Markets reports SM Energy’s wells “measure up well to anything being drilled in the Midland Basin by anybody today.”
Vår Selling Norne Assets to DNO
2024-05-08 - In exchange for Vår’s producing assets in the Norwegian Sea, DNO is paying $51 million and transferring to Vår its 22.6% interest in the Ringhorne East unit in the North Sea.
Crescent Energy: Bigger Uinta Frac Now Making 60% More Boe
2024-05-10 - Crescent Energy also reported companywide growth in D&C speeds, while well costs have declined 10%.
SLB OneSubsea JV to Kickstart North Sea Development
2024-05-07 - SLB OneSubsea, a joint venture including SLB and Subsea7, have been awarded a contract by OKEA that will develop the Bestla Project offshore Norway.