U.S. energy and safety regulators told Cheniere Energy Inc. on July 9 the company had to take several steps before the agencies would authorize the return to service of two LNG storage tanks that leaked at the Sabine Pass LNG export terminal in Louisiana.
The U.S. Department of Transportation’s Pipeline and Hazardous Materials Safety Administration (PHMSA) and the Federal Energy Regulatory Commission (FERC) told Cheniere that neither agency is prepared to authorize a return to service at this time.
In April 2018, Cheniere agreed to take certain corrective measures, but the agencies said in their filing that the company has in some instances “failed to comply” with requests to test equipment and provide documentation of the testing.
In response, Cheniere, the biggest U.S. LNG exporter, said in an email, “We are analyzing the letter from the agencies and will provide a formal response. We have been responsive and forthcoming throughout this process, and will continue to be.”
PHMSA ordered Cheniere to shut two LNG storage tanks on Feb. 8, 2018, after plant workers on Jan. 22, 2018, discovered a 1-to-6-foot-long crack at one tank that leaked fuel into an outer layer. During the investigation of the Sabine site, PHMSA discovered a second tank had also experienced releases of LNG from the inner tank.
The agencies told Cheniere that any work done to return a tank to service prior to completion of the agencies’ requirements is “at your own risk.”
The agencies noted PHMSA has previously conveyed its concern to Cheniere regarding premature filling of one tank with perlite, which is used to insulate LNG tanks.
Some of the tasks the agencies said Cheniere would have to complete before allowing the tanks to return to service include a structural reinspection of all LNG storage tanks at Sabine and installation of additional devices to detect leaks.
There are five tanks at Sabine, each with the capacity to hold the equivalent of 3.4 billion cubic feet of gas (Bcf), or 17 Bcf in total. One billion cubic feet of gas is enough to fuel about 5 million U.S. homes for a day.
Recommended Reading
Objection: Energy Execs Indict DC Appellate Court’s LNG Rulings
2024-08-26 - An ongoing battle with the D.C. Court of Appeals may affect all future FERC-related projects.
NextDecade CEO: LNG Ruling Risks Viability of All FERC Projects
2024-08-14 - NextDecade Chairman and CEO Matt Schatzman said an Aug. 6 ruling by the U.S. Court of Appeals for the D.C. Circuit to vacate its FERC permit has “far-reaching implications” that could undercut capital investment in LNG projects.
Bipartisan Bill Aims to Speed Up Permitting Bureaucracy
2024-07-23 - If passed, the new rules would tackle litigation delays for energy projects across all sectors, an analyst says.
Supreme Court’s Uinta Basin Rail Case Raises Stakes for LNG, Pipelines
2024-07-10 - The lawsuit, involving crude transport via railway in the Uinta Basin, is part of a larger intragovernmental fight that could have implications for how FERC decides pipeline and LNG plant permitting.
FERC Re-affirms Tellurian Extension Request for Driftwood LNG
2024-07-09 - The Federal Energy Regulatory Commission upheld its earlier decision following the Sierra Club’s request for another hearing on Driftwood LNG’s 2029 completion date.