Top executives with Chevron Corp. continue to eye massive production growth from the company’s Permian assets while also acknowledging some shortcomings in the Delaware Basin.
“The headline is our production guidance is unchanged, 3% compounded annual growth rate over the next five years,” Chevron chairman and CEO Mike Wirth said Feb. 28 during the company’s annual Investor Day 2023 event in New York.
In the Permian, Wirth said the target was still to reach 1 MMboe/d by 2025 with a plateau later in the decade of approximately 1.2 MMboe/d. Average production in the Permian was around 738,000 boe/d in the fourth quarter of 2022 while total net global production was 3 MMboe/d.
The company reported that it’s Midland Basin operations had performed well while the Delaware saw problems related to DUCs and horizontal wells.
Wirth said the company continues to learn every year in the Permian and its sub-basins.
“It's not a homogeneous geologic setting there, it’s a lot of heterogeneity, and where a single bench may work in one area better than multiple other areas where the inverse is the case,” Wirth said.
The California-based energy major remains confident in exceeding its five-year annual production growth guidance owing to Tengiz, Gulf of Mexico and other shale and tight assets in addition to the Permian, Chevron executive vice president of oil, products and gas Nigel Hearne said during his opening remarks at the event.
The Permian Basin spans parts of west Texas and southeastern New Mexico and covers an area about 250 miles wide and 300 miles long. It includes the highly-prolific Delaware and Midland sub-basins.
Delaware Basin hiccups
Chevron has a long history in the Permian and through its legacy companies has been active in the shale basin since the early 1920s.
“The Permian continues to deliver higher returns, production growth and lower carbon intensity,” Hearne said. “Last year performance in the Midland Basin exceeded our plans but fell short in the Delaware primarily due to higher-than-expected depletion after completing long-sitting DUCs.”
“In the Midland Basin performance plan in the Delaware we fell short and there are a few reasons, primarily driven by completion,” Hearne said during the question and answer portion of the event.
“We saw some wells impacted by horizontal interference and long sitting DUCs,” he continued. “We saw some vertical interference where we pilot multi-bench development primarily on the southern area of the Delaware Basin, on the western area of the Delaware Basin.”
Hearne said Chevron’s large inventory allows it to shift its operated program to more single bench, high-return developments in New Mexico.
Despite the hiccups, Wirth reiterated that Chevron’s long-term guidance for the Permian remains unchanged. He said the company continues to manage cost pressures and leverage technology to drive performance improvements.
“Examples include simulfrac, where we perform completion activities on four wells at the same time and optimized gas-lift, which lowers downtime, minimizes workovers and improves safety,” Hearne said. “This year we’ll be running four grid-powered rigs and one natural gas driven frac spread. Around 40% of our grid-supplied power will be from wind and solar.”
Recommended Reading
Dividends Declared in the Week of Aug. 19
2024-08-23 - As second-quarter earnings wrap up, here is a selection of dividends declared in the energy industry.
Gulfport Energy to Offer $500MM Senior Notes Due 2029
2024-09-03 - Gulfport Energy Corp. also commenced a tender offer to purchase for cash its 8.0% senior notes due 2026.
Pembina Completes Partial Redemption of Series 19 Notes
2024-07-08 - The redemption is part of Pembina Pipeline’s $300 million (US$220.04 million) aggregate principal amount of senior unsecured medium-term series 19 notes due in 2026.
Offshore Guyana: ‘The Place to Spend Money’
2024-07-09 - Exxon Mobil, Hess and CNOOC are prepared to pump as much as $105 billion into the vast potential of the Stabroek Block.
Bechtel Awarded $4.3B Contract for NextDecade’s Rio Grande Train 4
2024-08-06 - NextDecade’s Rio Grande LNG Train 4 agreed to pay Bechtel approximately $4.3 billion for the work under an engineering, procurement and construction contract.