Presented by:
Editor's note: This article appears in the special OTC edition of the E&P newsletter. Subscribe here.
Following its major upgrade, McDermott’s Amazon will be sailing the waters as one of the most technologically sophisticated offshore construction vessels.
Its upgraded specs enable highly automated operations, the production of hex joints from single or double joints using an onboard multi-joint facility and a pipe hold capacity of 10,000 metric tons.
“The new Amazon, once complete, will redefine our industry’s understanding of what is possible within ultradeepwater construction,” said Mladen Luketa, captain of McDermott’s Amazon vessel.
With 10,000 metric tons of pipe in its hold, the vessel will be capable of continuing pipelay operations long after the pipe-supply vessel transfers pipe. Its dynamic hex-joint J-lay system, which is 50% longer than a conventional quad-lay, will result in a 30% reduction in the number of critical path tower welds.
“The Amazon’s upgraded design creates new opportunities in the ultradeepwater arena that have never been attainable before,” said Michel Middel, McDermott’s executive project director of the Amazon Conversion. “It will also enable our clients to undertake ultradeepwater field development in remote locations with minimal supporting infrastructure.”
The Amazon's dynamic top tension J-lay system has a capacity of 1,500 metric tons and allows large diameter pipelines to be deployed in water depths up to 3,500 m—a major advantage in developing ultradeepwater reserves, especially in the Gulf of Mexico.
The Amazon’s high level of automation allows a significant reduction in the crew numbers required to safely perform pipelay operations, which is even more valuable than originally envisioned, especially as the world continues to navigate the challenges of operating safely during a global pandemic.
Construction and testing
The Amazon conversion recently entered its commissioning phase.
“Following a progressive program of harbor acceptance testing, the Amazon will be complete by the end of this year,” said Tony Brown, McDermott’s vice president of global marine assets and operations. “The completion of construction in Rotterdam will be followed by an intense two-week program of offshore testing to complete the acceptance and redelivery of the vessel."
Offshore testing is scheduled to start during the first quarter of next year to ensure the vessel is fully ready to execute the scope for its first project.
Earlier this year, McDermott achieved a major milestone in the construction phase of this project with the installation of its loader arm (LDA), the final major component to be installed during the conversion.
“This latest achievement was the culmination of months of hard work from the conversion team,” Brown said. “In total, the LDA weighs an incredible 504 tons. It is 85 meters in length, 8.5 meters wide and 8.6 meters high.”
It was fabricated in separate sections in a closed environment fabrication facility in Poland before being shipped to IHC’s Port of Blyth facility for final tie-in, followed by an extensive period of outfitting, acceptance testing and partial commissioning. Once ready, it was transported to Rotterdam by barge where it was prepared for final installation.
The LDA is used to transport hex (six joints), pent (five joints) or quads (four joints) from a horizontal position on the mezzanine deck to a vertical (or near vertical) position at the tower. Once docked, the LDA, outfitted with six longitudinal clamps, swings the pipe string into position in the tower ready for welding and coating. The entire assembly weighed in excess of 600 tons, and its full length was approximately 95 m.
“The LDA is a key component of the overall design of the Amazon’s pipelay system and is crucial to having a hex joint, ultradeepwater pipelay vessel,” said Stewart House, a McDermott engineering and mission equipment manager.
For more information, visit McDermott at booth 1565.
Recommended Reading
Lake Charles LNG Selects Technip Energies, KBR for Export Terminal
2024-09-20 - Lake Charles LNG has selected KTJV, the joint venture between Technip Energies and KBR, for the engineering, procurement, fabrication and construction of an LNG export terminal project on the Gulf Coast.
Entergy Picks Cresent Midstream to Develop $1B CCS for Gas-fired Power Plant
2024-09-20 - Crescent will work with SAMSUNG E&A and Honeywell on the project.
FERC Chair: DC Court ‘Erred’ by Vacating LNG Permits
2024-09-20 - Throwing out the permit for Williams’ operational REA project in the mid-Atlantic region was a mistake that could cost people “desperately” reliant on it, Chairman Willie Phillips said.
Diamondback to Sell $2.2B in Shares Held by Endeavor Stockholders
2024-09-20 - Diamondback Energy, which closed its $26 billion merger with Endeavor Energy Resources on Sept. 13, said the gross proceeds from the share’s sale will be approximately $2.2 billion.
Optimizing Direct Air Capture Similar to Recovering Spilled Wine
2024-09-20 - Direct air capture technologies are technically and financially challenging, but efforts are underway to change that.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.