The Federal Energy Regulatory Commission voted Feb. 15 to approve a cross-border pipeline segment that is part of a plan to take more U.S. natural gas to Mexico’s west coast for export.
The FERC voted in favor of a 48-inch diameter, 1,000-meter pipeline segment that crosses the Texas-Mexico border. The segment is part of the 655-mile ONEOK’s Saguaro Connector Pipeline, which is planned to follow a route from the Waha Hub in Pecos County to Puerto Libertad on Mexico’s West Coast.
RELATED: ONEOK Asks FERC to Grant Permian-Mexico Connector Pipeline
The segment that crosses the border is the only part of the line that requires federal approval, as the remainder of the line on the U.S. side is entirely within Texas borders.
Once completed, the line will have a capacity of about 2.8 Bcf/d. The LNG plant on Mexico’s coast has yet to reach final investment decision. Mexico Pacific LNG expects to spend about $15 billion on the LNG project.
The pipeline has been opposed by environmental groups and some of the people who live along the route, such as residents of the small West Texas town of Van Horn, where the line will pass within a mile of city limits.
Recommended Reading
CERAWeek: AI, Energy Industry Meet at Scary but Exciting Crossroads
2024-03-19 - From optimizing assets to enabling interoperability, digital technology works best through collaboration.
Tech Trends: AI Increasing Data Center Demand for Energy
2024-04-16 - In this month’s Tech Trends, new technologies equipped with artificial intelligence take the forefront, as they assist with safety and seismic fault detection. Also, independent contractor Stena Drilling begins upgrades for their Evolution drillship.
Tech Trends: Safety, Speed, Savings: Automation is Transforming Drilling
2024-03-26 - Drilling is getting smarter through automation, delivering efficiency, consistency and reliability.
TotalEnergies Rolling Out Copilot for Microsoft 365
2024-02-27 - TotalEnergies’ rollout is part of the company’s digital transformation and is intended to help employees solve problems more efficiently.
Defeating the ‘Four Horsemen’ of Flow Assurance
2024-04-18 - Service companies combine processes and techniques to mitigate the impact of paraffin, asphaltenes, hydrates and scale on production—and keep the cash flowing.