EPIC Crude Pipeline LP said the projected third-quarter start-up of its crude pipeline from the Permian basin to Corpus Christi, Texas is in "some jeopardy" after U.S. regulators delayed action on its petition to set initial tariff rates.
The San Antonio-based company said in a letter to U.S. Federal Energy Regulatory Commission dated Jan. 8 that the requested Jan. 4 action date for FERC to pass a declaratory order that would allow EPIC to set rates has "now come and gone," causing concern to shippers.
The planned 900,000 barrels-per-day (bbl/d) pipeline, stretching from Southeast New Mexico and West Texas to refineries and other destinations in and around Corpus Christi, is one of the largest lines currently under construction and is seen as vital for bringing crude out of the largest oil patch in the U.S.
Crude prices in the Permian basin have come under pressure in recent months as a production surge has overwhelmed existing pipeline and infrastructure, sparking a race to add new lines. Prices in Texas collapsed in 2018 due to full lines.
Currently, the Permian produces about 3.8 million bbl/d, accounting for about a third of overall U.S. production of 11.7 million bbl/d, according to U.S. Energy Department figures.
The pipeline was projected to be up and running to Corpus Christi by the third quarter.
EPIC filed a petition in October, asking for FERC's approval within about 90 days that would allow the company to start setting shipping rates on the line. Pipeline companies typically hold bidding rounds known as an open season to solicit shippers that commit to long-term contracts and fill the line with crude before commercial deliveries begin.
"We have had no indication from Commission Staff that any aspect of our project is problematic from a regulatory standpoint, but we are committed to addressing and resolving any issues that should arise in that regard," EPIC said in its letter, urging FERC to vote on the petition by Jan. 15.
EPIC currently has committed transportation agreements with five shippers, covering about 60% of the system's capacity, it said in the letter.
"The case is still under review," a FERC spokeswoman said.
EPIC was formed in 2017 and the crude line is one of its first projects. In October, EPIC said it would convert a portion of its planned NGL pipeline to transport crude instead.
Recommended Reading
Energy Transfer Asks FERC to Weigh in on Williams Gas Project
2024-04-08 - Energy Transfer's filing continues the dispute over Williams’ development of the Louisiana Energy Gateway.
Imperial Oil Shuts Down Fuel Pipeline in Central Canada
2024-03-18 - Supplies on the Winnipeg regional line will be rerouted for three months.
Balticconnector Gas Pipeline Will be in Commercial Use Again April 22, Gasgrid Says
2024-04-17 - The Balticconnector subsea gas link between Estonia and Finland was damaged in October along with three telecoms cables.
Williams Beats 2023 Expectations, Touts Natgas Infrastructure Additions
2024-02-14 - Williams to continue developing natural gas infrastructure in 2024 with growth capex expected to top $1.45 billion.
Venture Global Acquires Nine LNG-powered Vessels
2024-03-18 - Venture Global plans to deliver the vessels, which are currently under construction in South Korea, starting later this year.