Prosafe SE said Sept. 3 it had reached an agreement that will compensate the vessel accommodation owner for a 10-month deferral by Royal Dutch Shell Plc of a U.K. North Sea contract at the Shearwater platform.

According to a company release by Prosafe, Shell U.K. Ltd. agreed to defer and amend the contract for Prosafe’s Safe Zephyrus to provide accommodation services in support of the Shearwater platform turnaround.

As part of the agreement, Shell will compensate Prosafe through a fee considering the 10-month mobilization deferment.

In a statement commenting on the agreement, Prosafe CEO Jesper Kragh Andresen said: “Shell has been, and will continue to be, one of our most valued customers. The COVID-19 pandemic has impacted the industry hard—operator and contractor alike—and it has been encouraging to work with Shell to solve the mutual challenges in a way which resulted in an agreement for the 2021 Shearwater turnaround, and a stronger strategic collaboration thereafter.”

The revised firm duration of the contract of 115 days commences in March 2021 although Shell has the option of adding either 30 or 45 days to the front end resulting in an earlier commencement date. Shell retains the option to extend the contract after the firm duration by up to 30 days.

Additionally, Shell and Prosafe will strategically work closely for 2022 and 2023, maximizing opportunity to benefit both parties, according to the Prosafe release.