The COVID-19 pandemic has interrupted the development of Norway’s offshore oil and gas projects, pushing up costs and postponing startups, the government and oil company Equinor said Oct. 7.
The costs of ongoing projects rose by 13.2 billion Norwegian crowns ($1.4 billion) from a year ago on an inflation-adjusted basis, government documents showed, as COVID-19 restrictions stalled construction at several fields.
“The COVID-19 pandemic and weakened Norwegian (currency) have negatively impacted some of the projects, but the combined project portfolio is still very resilient,” Equinor said in a separate statement.
Following the delays, Norway’s oil output for next year is now expected to be 2.15 million barrels per day, slightly less than the 2.24 million predicted for 2021 one year ago, the government’s budget showed.
Gas production is expected to be 117 billion cubic meters (Bcm), less than 121 Bcm forecast a year ago.
Equinor’s Martin Linge oil and gas field is now expected to cost 60.8 billion crowns, up from an estimate of 56.1 billion a year ago, Norway’s 2021 fiscal budget showed.
The company’s Johan Castberg Arctic oil field, meanwhile, is now expected to cost 53.4 billion crowns, up from 49 billion crowns previously, the government said.
Cost overruns also hit Equinor’s Njord Future, Repsol’s Yme and other developments.
In March, the long-delayed Martin Linge development became the first offshore field to be hit by the pandemic when installation work was halted after an employee tested positive for the virus.
Half of the inflation-adjusted cost increase of 3.6 billion crowns for Martin Linge was down to infection control measures, Equinor said.
The pandemic also interrupted construction of the Johan Castberg’s FPSO unit at a yard in Singapore, while the company also discovered technical problems.
Both projects have been delayed by about a year, with Martin Linge now expected to come on stream in the summer of 2021 and Johan Castberg in the fourth quarter of 2023.
The cost of the Njord Future project, which aims to produce an extra 175 million barrels of oil equivalent from Njord, and its tie-back Hyme also rose. The planned startup date has been delayed until next year.
As a result, several smaller projects, which are planning to use the Njord’s production facilities, such as Neptune Energy’s Fenja, will also be delayed.
Recommended Reading
Uinta Basin: 50% More Oil for Twice the Proppant
2024-03-06 - The higher-intensity completions are costing an average of 35% fewer dollars spent per barrel of oil equivalent of output, Crescent Energy told investors and analysts on March 5.
Crescent Point Energy to Rebrand as Veren Inc.
2024-03-21 - The company will seek shareholder approval for the change at its upcoming annual and special meeting of shareholders on May 10.
Kimmeridge Fast Forwards on SilverBow with Takeover Bid
2024-03-13 - Investment firm Kimmeridge Energy Management, which first asked for additional SilverBow Resources board seats, has followed up with a buyout offer. A deal would make a nearly 1 Bcfe/d Eagle Ford pureplay.
Laredo Oil Subsidiary, Erehwon Enter Into Drilling Agreement with Texakoma
2024-03-14 - The agreement with Lustre Oil and Erehwon Oil & Gas would allow Texakoma to participate in the development of 7,375 net acres of mineral rights in Valley County, Montana.
SLB’s ChampionX Acquisition Key to Production Recovery Market
2024-04-19 - During a quarterly earnings call, SLB CEO Olivier Le Peuch highlighted the production recovery market as a key part of the company’s growth strategy.