Editor's note: This article originally appeared on EnerKnol. Subscribe here.
The New York Independent System Operator Inc.'s board of directors selected two transmission projects, which would add the largest amount of capacity to the state's power grid in over 30 years, according to an April 8 press release.
The grid operator said the aging and congested transmission infrastructure is not capable of accommodating the state's goal of obtaining half its electricity from renewable resources by 2030, as well as the new goals being discussed under the recently announced "Green New Deal" to achieve carbon neutrality.
The state's Public Service Commission identified the need to expand transmission infrastructure to deliver power from generating facilities, including renewable resources, sited in the upstate region to the population centers located downstate.
Among the projects, "Segment A," designed to expand the transmission capability from central to eastern New York by at least 350 megawatts, will be jointly developed by North America Transmission and New York Power Authority. "Segment B," intended to increase the capability from the Albany region through the Hudson Valley region by 900 megawatts, will be built by National Grid plc and New York Transco LLC.
The projects are estimated to cost $1,230 million including a 30% contingency.
The selection comprises the second and third transmission projects to go through the "Public Policy Transmission Planning Process," required by the Federal Energy Regulatory Commission. The first one was a proposal by NextEra, which won approval in October 2017 for a transmission project in Western New York to aid delivery from hydroelectric generation.
The planning process considers transmission needs driven by public policy requirements established by the state.
EnerKnol is a provider of regulatory data, analytics, and tracking software for North American energy markets.
Recommended Reading
U.S. Energy Corp. Declares Quarterly Cash Dividend
2023-05-09 - The dividend of $0.0225 per share will be payable on May 30.
E&P Highlights: March 13, 2023
2023-03-13 - Here’s a roundup of the latest E&P headlines including first gas offshore Egypt and FEED updates in the upstream oil and gas industry.
EQT Declares Quarterly Cash Dividend
2023-04-20 - EQT Corp.'s board of directors declared a quarterly cash dividend of $0.15 per share, to be paid out on June 1.
DT Midstream Announces Quarterly Dividend
2023-05-08 - DT Midstream’s board of directors declared a $0.69 per share quarterly dividend on its common stock.
Matador Declares $0.15 Per Share Quarterly Cash Dividend
2023-04-20 - Matador Resources’ quarterly cash dividend of $0.15 per share will be payable on June 1 to shareholders on record as of May 11.