A U.S. appeals court on Sept. 10 barred PennEast Pipeline Co. from using a federal law to seize properties controlled by the state of New Jersey in order to build a proposed $1 billion natural gas pipeline.
The U.S. Court of Appeals for the Third Circuit said in its decision that the U.S. Natural Gas Act does not allow companies to condemn state controlled land in federal court because states enjoy sovereign immunity from such actions under the Eleventh Amendment of the U.S. Constitution.
PennEast obtained approval from the U.S. Federal Energy Regulatory Commission to build the pipeline from Pennsylvania to New Jersey in January 2018 and promptly sued in federal district court to use the federal government’s eminent domain power to gain access to 131 properties along the route in New Jersey under the U.S. Natural Gas Act.
New Jersey, which opposes construction of the pipe, did not consent to PennEast’s condemnation suits on 42 of the 131 properties it controls. The state holds possessory interests in two of the properties and non-possessory interests in the rest, most often through easements requiring the land be preserved for recreational, conservation or agricultural use.
PennEast needs the land to build its 120-mile pipeline, which is designed to deliver gas from the Marcellus Shale formation in Pennsylvania to customers in Pennsylvania and New Jersey.
The Third Circuit decision reverses an earlier district court ruling that had allowed PennEast to condemn the state controlled properties.
“We will not hesitate to stand up to private companies when their actions violate the law—or, in this case, the U.S. Constitution,” New Jersey Attorney General Gurbir Grewal said in a statement.
Patricia Kornick, a spokeswoman for PennEast, said the company “will review the Third Circuit Court’s opinion and determine what our next steps will be.”
She said the company anticipates starting construction on the pipeline in 2020.
The companies seeking to build PennEast include units of New Jersey Resources Corp. (NJR), South Jersey Industries Inc. (SJI), Southern Co., Enbridge Inc. and UGI Corp.
The companies with contracts to use the project include units of NJR, SJI, Southern, Public Service Enterprise Group Inc. and Consolidated Edison Inc.
Recommended Reading
US EPA Expected to Drop Hydrogen from Power Plant Rule, Sources Say
2024-04-22 - The move reflects skepticism within the U.S. government that the technology will develop quickly enough to become a significant tool to decarbonize the electricity industry.
Exclusive: ‘Regulatory Tsunami’ a Top Priority for American Producers, Says AXPC’s Bradbury
2024-04-22 - Regulatory considerations have significant implications for how oil and gas companies evaluate risk, and it’s a top priority for American energy producers right now, said American Exploration & Production Council CEO Anne Bradbury at CERAWeek by S&P Global.
Biden Administration Criticized for Limits to Arctic Oil, Gas Drilling
2024-04-19 - The Bureau of Land Management is limiting new oil and gas leasing in the Arctic and also shut down a road proposal for industrial mining purposes.
Exclusive: The Politics, Realities and Benefits of Natural Gas
2024-04-19 - Replacing just 5% of coal-fired power plants with U.S. LNG — even at average methane and greenhouse-gas emissions intensity — could reduce energy sector emissions by 30% globally, says Chris Treanor, PAGE Coalition executive director.
Renewed US Sanctions to Complicate Venezuelan Oil Sales, Not Stop Them
2024-04-19 - Venezuela’s oil exports to world markets will not stop, despite reimposed sanctions by Washington, and will likely continue to flow with the help of Iran—as well as China and Russia.