Neptune Energy has conducted the world’s first dual drilling operation from an integrated subsea template structure at the Fenja field in the Norwegian North Sea on May 13.
In conjunction with the start-up of the Fenja drilling campaign last month, Neptune teams maximized the full capabilities of Seadrill’s West Phoenix drilling rig to drill two wellbores at the same time.
While many drilling rigs are equipped with dual drilling capabilities, this was the first time dual drilling has been executed from an integrated subsea template structure. This accelerated the drilling operations, reduced costs and lowered operational emissions.
“Several drilling rigs have two drilling facilities where these traditionally support one another. However, in the instance of our operations we decided to use these facilities independently to concurrently drill two wellbores,” Thor Andre Løvoll, Neptune’s director of drilling and wells in Norway, said.
“The experience of dual drilling on Fenja has been positive and could see this method adopted as a more standard practice in the future. The current challenges in the market encourage us to re-think the way we do things safely, efficiently and with lower carbon emissions.”
Neptune recently conducted dual drilling operations on an exploration well on the Norwegian Continental Shelf and the experience was applied towards the Fenja subsea field development with great success.
Fenja is Neptune’s first operated development project on the Norwegian Shelf and is estimated to contain 97 million barrels of oil equivalent (boe). Fenja will deliver around 40,000 boe per day at plateau.
Located in the Norwegian Sea 120 km north-west of Kristiansund at a water depth of 320 m, the subsea field will be developed as a tie-back to the Njord-A platform. At 36 km, it will be the world’s longest electrically trace-heated pipe-in-pipe subsea development.
Recommended Reading
US Raises Crude Production Growth Forecast for 2024
2024-03-12 - U.S. crude oil production will rise by 260,000 bbl/d to 13.19 MMbbl/d this year, the EIA said in its Short-Term Energy Outlook.
ONGC’s M Field Starts Production in Bay of Bengal
2024-01-09 - ONGC’s M Field represents the second phase of the larger 98/2 Block development project which is expected to reach peak production of 45,000 bbl/d and 10 MMcm/d.
US Drillers Cut Oil, Gas Rigs for Second Week in a Row
2024-01-12 - The oil and gas rig count, an early indicator of future output, fell by two to 619 in the week to Jan. 12, the lowest since November.
US Drillers Cut Oil, Gas Rigs for Third Week in a Row
2024-01-05 - The oil and gas rig count, an early indicator of future output, fell by one to 621 in the week to Jan. 5.
Trio Petroleum to Restart McCool Ranch Oilfield
2024-01-07 - California’s Trio Petroleum plans to restart oilfield production at McCool Ranch, where six wells that previously reached a production peak of 400 bbl/d.