Kinder Morgan Inc. can begin work on a $2 billion natural gas pipeline without having the Texas energy regulator approve its proposed route, a state judge ruled on June 25.
The decision removes a challenge to the state’s licensing process that lets gas pipeline companies determine their own route and acquire land without a landowner’s consent. Texas is in the midst of a pipeline-construction boom with multibillion-dollar projects under way to bring shale oil and gas to market.
A Travis County District court ruled the Texas Railroad Commission, the state’s oil and gas regulator, is not required to set standards for routing the pipelines or private land-takings, Judge Lora Livingston wrote on June 25. The state allows gas pipeline operators that qualify as utilities to use eminent domain to take land for the public good.
“The court finds no authority for the proposition that the legislature has granted authority to the Commission to oversee the rights granted,” she wrote. She also granted Kinder Morgan’s request to dismiss it from the lawsuit.
A group of Texas landowners and officials had sued to block construction, arguing the oil and gas regulator failed to seek public input or properly supervise the routing of Kinder Morgan’s Permian Highway Pipeline, which will carry 2 billion cubic feet per day of natural gas roughly 645 km (400 miles) from West Texas to the U.S. Gulf Coast.
Kinder Morgan had asked the court to throw out the landowners’ lawsuit, arguing it was up to the state legislature, not the court, to change the pipeline permitting process.
“The court’s finding validates the process established in Texas for the development of natural gas utility projects,” Tom Martin, a Kinder Morgan executive, said on June 25.
U.S. shale gas production in July is projected to hit a record 81.4 billion cubic feet per day, which would be an 18th consecutive monthly increase. Shale oil could hit 8.52 million barrels per day that same month, according to the U.S. Energy Information Administration.
Landowners argued that the pipeline will cross “sensitive environmental features,” such as endangered species habitats, sites of historical significance and residential subdivisions, according to a filing.
The Texas Real Estate Advocacy and Defense Coalition, which advocates for Texas landowner rights, said it was weighing an appeal and additional legal actions in other venues.
The ruling “is unfortunate but not unexpected,” said Travis Mitchell, mayor of Kyle, Texas, a co-plaintiff. “We will be working to determine the best path forward. We’re certainly not giving up.”
A spokeswoman for the Railroad Commission of Texas declined to comment.
Recommended Reading
E&P Earnings Season Proves Up Stronger Efficiencies, Profits
2024-04-04 - The 2024 outlook for E&Ps largely surprises to the upside with conservative budgets and steady volumes.
Petrie Partners: A Small Wonder
2024-02-01 - Petrie Partners may not be the biggest or flashiest investment bank on the block, but after over two decades, its executives have been around the block more than most.
CEO: Coterra ‘Deeply Curious’ on M&A Amid E&P Consolidation Wave
2024-02-26 - Coterra Energy has yet to get in on the large-scale M&A wave sweeping across the Lower 48—but CEO Tom Jorden said Coterra is keeping an eye on acquisition opportunities.
Endeavor Integration Brings Capital Efficiency, Durability to Diamondback
2024-02-22 - The combined Diamondback-Endeavor deal is expected to realize $3 billion in synergies and have 12 years of sub-$40/bbl breakeven inventory.
Exxon, Chevron Tapping Permian for Output Growth in ‘24
2024-02-02 - Exxon Mobil and Chevron plan to tap West Texas and New Mexico for oil and gas production growth in 2024, the U.S. majors reported in their latest earnings.