The companies developing the Mountain Valley Southgate natural gas pipeline expansion from Virginia to North Carolina said on Aug. 12 they continue to target a 2021 startup for the project after North Carolina regulators denied a water permit.
The North Carolina Department of Environmental Quality (DEQ) denied the permit on Aug. 11 due to uncertainty around whether Equitrans Midstream Corp. will complete the $5.4-$5.7 billion Mountain Valley Pipeline (MVP) from West Virginia to Virginia. A unit of Equitrans is leading the MVP project.
“We are disappointed by the decision,” project spokesperson Shawn Day said, noting “Work on MVP is 92% complete and is targeted to enter service in early 2021.”
MVP is one of several U.S. pipelines delayed by regulatory and legal fights with environmental and local groups that found problems with federal permits issued by the Trump administration.
Other projects similarly held up include Dominion Energy Inc.’s recently canceled $8 billion Atlantic Coast gas pipe from West Virginia to North Carolina.
“(Southgate) has always been an unnecessary project that poses unnecessary risks to our environment and given the uncertain future of the MVP Mainline. North Carolinians should not be exposed to the risk of another incomplete pipeline project,” DEQ Secretary Michael Regan said in a statement.
“North Carolina’s clean energy future is not dependent on adding more gas infrastructure,” Regan said.
The North Carolina rejection caused some analysts to question whether Equitrans will be able to finish Southgate by the end of 2021, if ever.
Recommended Reading
Riley Exploration Permian Declares Quarterly Cash Dividend
2024-01-17 - Riley Exploration Permian’s February quarterly cash dividend is the 20th consecutive distribution made by the company.
TotalEnergies Ups Stake in Two Blocks Offshore Namibia
2024-01-10 - TotalEnergies is acquiring an additional 10.5% participating interest in Block 2913B and an additional 9.39% participating interest in Block 2912.
From Restructuring to Reinvention, Weatherford Upbeat on Upcycle
2024-02-11 - Weatherford CEO Girish Saligram charts course for growth as the company looks to enter the third year of what appears to be a long upcycle.
CorEnergy Infrastructure to Reorganize in Pre-packaged Bankruptcy
2024-02-26 - CorEnergy, coming off a January sale of its MoGas and Omega pipeline and gathering systems, filed for bankruptcy protect after reaching an agreement with most of its debtors.
Baytex Prices Upsized Private Placement of Senior Notes
2024-03-15 - Baytex intends to use the proceeds to pay a portion of outstanding debt on its credit facilities and general corporate purposes.