
(Source: EQM Midstream Partners LP)
EQM Midstream Partners LP delayed the expected completion of its Mountain Valley natural gas pipeline from West Virginia to Virginia to early 2021 and said it could boost the $5.4 billion project’s cost by 5% to around $5.7 billion.
Industry analysts, however, said Mountain Valley and other U.S. pipelines will likely be delayed even further by a Montana court’s decision that the U.S. Army Corps of Engineers did not comply with the Endangered Species Act.
EQM, which changed the projected in-service date in a statement issued late June 11, had previously said it expected Mountain Valley to enter service in late 2020.
“We are confident in the ultimate completion of this important infrastructure project,” EQM COO Diana Charletta said, noting it was about 92% complete.
When EQM started construction in February 2018, it estimated Mountain Valley would cost about $3.5 billion and be completed by the end of 2018.
But successful legal challenges to federal permits resulted in lengthy delays and higher costs for Mountain Valley and other gas pipes, like Dominion Energy Inc.’s $8 billion Atlantic Coast line from West Virginia to North Carolina.
Analysts at Height Capital Markets in Washington said on June 12 that EQM’s new in-service date and potential cost increase are optimistic given legal issues with the Army Corps’ Nationwide Permit 12 program, which Mountain Valley intends to use to cross the remaining 10 miles of water bodies along its route.
In April, a Montana judge ruled the Army Corps violated federal law by issuing Nationwide Permits to cross water bodies without adequately consulting other agencies on risks to endangered species and habitat.
“Besides the (Nationwide Permit) issue, Mountain Valley faces litigation risk on several upcoming permitting decisions,” Height Capital Markets said, noting the project will likely enter service in second-quarter 2021.
Recommended Reading
US Oil/Gas Rig Count Down for 11th Week to Lowest Since 2021, Baker Hughes Says
2025-07-11 - U.S. energy firms this week cut the number of oil and natural gas rigs operating for an 11th week in a row for the first time since 2020.
EQT Bags 1-Bcf/d Marcellus Deal for Data Center Power Plant
2025-07-15 - The Frontier Group of Companies plans to use gas supplied by EQT to convert a shuttered coal-fired power plant northwest of Pittsburgh to a gas-fired development in support of a new data center.
US Drillers Add Oil, Gas Rigs for Second Week in a Row
2025-04-25 - The oil and gas rig count rose by two to 587 in the week to April 25. Despite this week's rig increase, Baker Hughes said the total count was still down 26, or 4% below this time last year.
NextEra: US Power Demand Will Call for Extra 71 Bcf/d Equivalent
2025-04-29 - NextEra Energy expects that of the total 450 GW of new electricity demand in the coming few years, 75 GW will be gas-fired—or some 12 Bcf/d. But turbines and skilled labor are needed.
Ghana Extends Production Licenses to 2040 for Two Fields
2025-06-05 - The MOU with Kosmos Energy, Tullow Oil, Ghana National Petroleum and others includes approval to drill up to 20 more wells in the Jubilee field.