Construction work at Equinor ASA’s Peregrino oil field off the coast of Brazil has been delayed by roughly two months, according to two sources with knowledge of the matter, as logistical difficulties surrounding the novel coronavirus take their toll on the nation's offshore oil industry.
Peregrino is Equinor’s largest offshore operation outside Norway, and produces 70,000 to 80,000 barrels per day of oil, according to the company’s website. Currently, Peregrino is composed of two fixed oil platforms attached to a FPSO.
Equinor is installing a third oil platform, which will add 273 million barrels of recoverable reserves to the 400 million Peregrino is known to hold. Equinor has said it plans to produce first oil from the new platform by the end of the year.
However, two sources with knowledge of the construction, granted anonymity to discuss private operational matters, said certain labor-intensive operations were being postponed due to social distancing measures being adopted by the company.
One source estimated the process of connecting the new platform to the FPSO, a vital step, was being delayed by roughly two months.
In a statement, Equinor acknowledged it had adjusted its operations due to the novel coronavirus but said it was premature to determine its effects on its construction schedule.
“Equinor’s first priority is ensuring the safety of our employees and suppliers working for us,” Equinor spokesman Erik Haaland wrote in an email.
“The offshore completion activities continue at the C platform, but manning is reduced as a preventive measure to reduce risk of spreading the virus. It is too early to conclude any schedule effects of this.”
The coronavirus has emerged as a significant concern for Brazil’s offshore oil industry.
As in other parts of the world, major oil firms are instituting mandatory quarantines and monitoring programs for employees before they embark offshore, and companies have widely extended offshore shifts by one to two weeks to decrease the turnover of personnel. Many non-essential maintenance activities have been postponed.
On April 14, national oil regulator ANP divulged that some 74 oil workers who had recently been on offshore installations in Brazil has tested positive for coronavirus. It said there were 897 suspected cases in the industry as a whole.
Recommended Reading
Utah’s Ute Tribe Demands FTC Allow XCL-Altamont Deal
2024-04-24 - More than 90% of the Utah Ute tribe’s income is from energy development on its 4.5-million-acre reservation and the tribe says XCL Resources’ bid to buy Altamont Energy shouldn’t be blocked.
Mexico Presidential Hopeful Sheinbaum Emphasizes Energy Sovereignty
2024-04-24 - Claudia Sheinbaum, vying to becoming Mexico’s next president this summer, says she isn’t in favor of an absolute privatization of the energy sector but she isn’t against private investments either.
Venture Global Gets FERC Nod to Process Gas for LNG
2024-04-23 - Venture Global’s massive export terminal will change natural gas flows across the Gulf of Mexico but its Plaquemines LNG export terminal may still be years away from delivering LNG to long-term customers.
US EPA Expected to Drop Hydrogen from Power Plant Rule, Sources Say
2024-04-22 - The move reflects skepticism within the U.S. government that the technology will develop quickly enough to become a significant tool to decarbonize the electricity industry.