Subsea efforts continue to focus on two fronts: first, reducing the flow of oil spilled by physical containment and second, further work on stopping the flow using a “top kill” option.
The containment dome that was deployed last week has been parked away from the spill area on the sea bed. Efforts to place it over the main leak point were suspended at the weekend as a build up of hydrates prevented a successful placement of the dome over the spill area.
A second, smaller containment dome is being readied to lower over the main leak point. The small dome will be connected by drill pipe and riser lines to a drill ship on the surface to collect and treat oil. It is designed to mitigate the formation of large hydrate volumes. This operation has never been done before in 5,000 feet of water.
In addition, further work on the blow out preventer has positioned us to attempt a “top kill” option aimed at stopping the flow of oil from the well. This option will be pursued in parallel with the smaller containment dome over the next two weeks.
All of the techniques being attempted or evaluated to contain the flow of oil on the seabed involve significant uncertainties because they have not been tested in these conditions before.
BP continues to do everything it can, in conjunction with governmental authorities and other industry experts, to find a solution to stem the flow of oil on the seabed.
Work on the first relief well, which began on Sunday May 2, continues. It is expected to take some three months to complete.
Surface Spill Response and Containment Work continues to collect and disperse oil that has reached the surface of the sea. More than 275 vessels are being used, including skimmers, tugs, barges and recovery vessels.
The volume of dispersant applied to the spill on the surface amounts to over 315,000 gallons since the spill response began.
Intensive operations to skim oil from the surface of the water also continued. Some 90,000 barrels of oily liquid has now been recovered.
The total length of deployed boom is now more than 1 million feet as part of the efforts to stop oil reaching the coast.
The cost to date of the response amounts to about $350 million, including the cost of spill response, containment, relief well drilling, commitments to the Gulf Coast States, settlements and federal costs.
Recommended Reading
Wave of Foreign Investment in US Gas Could Top $10B
2025-06-04 - A wave of U.S. gas deals is coming, and international giants from Asia to the Middle East are circling, says Greenhill’s Jeet Benipal at Hart Energy’s Energy Capital Conference.
Texas’ RRC Approves Salt Dome NatGas Storage Project Near Houston
2025-06-18 - The Gulf Coast Midstream Partners’ FRESH facility would add about 26 Bcf of storage to southeast Texas in its first phase. The project is pending a final investment decision.
Jury Sides with Marathon in $123.7MM Force Majeure Case
2025-05-07 - At the peak of Winter Storm Uri between Feb. 15 and Feb. 20, 2021, Marathon faced a force majeure event in fulfilling its supply contract with Koch Energy Services.
Aethon Balances Supply-Demand with Haynesville ‘Storage Piece’
2025-07-16 - Aethon Energy Management’s Gordon Huddleston said the private investment firm has a game plan for its Haynesville asset to balance the natural gas supply-demand equation.
Enbridge Keeps the Focus on NatGas Amid Market Uncertainty
2025-05-09 - Enbridge CEO Greg Ebel said the company remains committed to growing its natural gas network.