Calcasieu Pass LNG is located south of Lake Charles in Southwestern Louisiana. The plant is designed to deliver 10 million tons of LNG per year (mtpa), liquefying up to 1.3 Bcf/d of natural gas. (Source: Shutterstock/ Venture Global)
Venture Global (VG) has permission to put all remaining facilities at the Calcasieu Pass LNG plant into service, the U.S. Federal Energy Regulatory Commission (FERC) said.
In a letter dated April 3, the FERC notified Venture Global that the remaining facilities associated with the plant that first produced LNG in 2022, had passed all required inspections.
“Based on Commission staff inspections and review of the commissioning and remediation activities, Venture Global has demonstrated that the above-mentioned facilities have been constructed in accordance with Commission approval and applicable standards and can be expected to operate safely and reliably as designed,” the FERC spokesman said.
Calcasieu Pass LNG is located south of Lake Charles in Southwestern Louisiana. The plant is designed to deliver 10 million tons of LNG per year (mtpa), liquefying up to 1.3 Bcf/d of natural gas.
Venture Global remains in an ongoing dispute with long-term clients that have contracted LNG from Calcasieu. Its resolution remains undetermined as of press time.
Since production began, the plant has delivered about 400 cargos, according to a report from Natural Gas Intelligence. All cargos were delivered on the spot market, allowing VG to bring in potentially higher fees than it would have otherwise from supplying its customers.
While the plant was still commissioning, Venture Global held that it had not reached a complete status and therefore was not required to supply its long-term customers.
The long-term customers, including Shell, BP, Edison and Repsol, disagreed and started arbitration proceedings against Venture Global at the end of 2024.
In mid-February, Venture Global said it would begin shipping to its long-term customers with the start of commercial operations.
VG’s customers were not convinced.
“We remain skeptical of their intent to fulfill their obligation to provide the cargos,” Shell said in a statement to Reuters on Feb. 18.
On April 3, Shell informed Hart Energy that the company had nothing to add. BP and Venture Global did not immediately respond to inquiries from Hart.
Recommended Reading
Energy Trader Vitol Eyes $3B Sale of US Shale Producer, Sources Say
2025-03-27 - Global commodities trader Vitol is exploring a sale of its VTX Energy Partners business, in a deal that could value the U.S. shale oil and gas producer at as much as $3 billion, including debt, people familiar with the matter said.
VAALCO Acquires 70% Interest in Offshore Côte D’Ivoire Block
2025-03-03 - Vaalco Energy announced a farm-in of CI-705 Block offshore West Africa, which it will operate under the terms of an acquisition agreement.
Iron Oak Energy Expands in Permian with High Roller Sand Deal
2025-04-08 - Proppant supplier Iron Oak Energy Solutions LLC is expanding in the Permian Basin with the acquisition of High Roller Sand for an undisclosed price.
Petro-Victory Completes Acquisition of Brazil’s Capixaba Energia
2025-04-30 - Petro-Victory partnered with BlueOak Investments to complete the $17.5 million deal for Brazilian E&P Capixaba Energia.
Flotek Buys Power Generation Assets from ProFrac for $105MM
2025-04-29 - Flotek Industries Inc. said the assets include digitally enhanced mobile natural gas conditioning and distribution units to provide real-time gas monitoring and dual fuel optimization.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.