After the years-long battle to build the Mountain Valley Pipeline (MVP), analysts say the Appalachian Basin’s natural gas industry will have to wait a while longer to reap the benefits.
On June 14, Equitrans Midstream, the line’s operator, said MVP had officially entered service, although Equitrans has not specified when gas on the 2 Bcf/d pipeline will begin to flow.
“This is an important and long-awaited day for our Nation and the millions of Americans who now have greater access to an abundant supply of domestic natural gas for use as an affordable, reliable, and cleaner energy resource,” said Diana Charletta, Equitrans president and CEO. “Natural gas is an essential fuel for modern life, and, as a critical infrastructure project, the Mountain Valley Pipeline will play an integral role in achieving a lower-carbon future while helping to ensure America’s energy and economic security for decades to come.”
Jim Crews, vice president of business development for MPLX and vice president of GO-WV, the Gas & Oil Association of West Virginia, said he was “Elated that MVP received FERC (Federal Energy Regulatory Commission) authority to put the pipe in service.”
The $7.85 billion project has dealt with multiple setbacks, protests and legal battles since construction began in 2018. In 2023, Congress wrote into law a provision directing agencies to grant the required environmental permits for completion. Nevertheless, MVP continued to face legal challenges, including a related Supreme Court case challenging FERC’s eminent domain authority.
“Obviously, we're discouraged about the time that it took to get it in service after so much support and such low prices that our producer members have experienced here in the Appalachian Basin,” Crews said.
Natural gas companies and power generators in the region hope to see better returns for their product.
The 42-inch MVP line flows 303 miles from West Virigina’s Wetzel County to Pittsylvania County, on the southern border of Virginia, where it can access Williams Cos.’ Transcontinental Pipeline. The line stretches from Texas to Pennsylvania. Zone 5 includes Virginia, North Carolina and South Carolina.
Crews said the local price points for much of Appalachia often run $1 lower than the NYMEX rate, thanks to Appalachia region’s lack of takeaway capacity.
“We're hoping that our members can get some relief on the gas price once the MVP starts flowing and accessing the Transco Zone 5 market down in Virginia and North Carolina,” Crews said.
The pipeline will help meet natural gas demand in Southwest Virginia, which continues to grow, said Paul Nester, president and CEO of utility Roanoke Gas Co.
“The MVP and its natural gas supply are essential to meeting the needs of residents and businesses across the Roanoke Valley, now and for many years to come,” Nester said. “Further, MVP’s delivery points to Roanoke Gas in Franklin and Montgomery Counties are certain to provide direct, long-term economic benefits to our community and this region.”
After all the legal and regulatory paperwork, permits and lawsuits, FERC approved the startup of the MVP following a June 11 phone call. Analysts said ramping up the pipeline’s operations would take months and that it could be more than a year before the line is running at full capacity.
East Daley Analytics forecast that the new pipeline would have modest impacts in the near term, flowing at about 750 MMcf/d, or nearly 38% capacity, according to its report. The line is waiting for a debottlenecking project, the Transco Southeast Supply Enhancement expansion, which is expected to be completed in 2027.
RELATED
Mountain Valley Pipeline’s ‘Phantom Takeaway’ Problem
Equitrans is also developing the Southgate Expansion to extend the line into North Carolina. The project is expected to be completed in 2028. In March, Equitrans agreed to a $5.45 billion merger with gas producer EQT. In the merger agreement, EQT specified that the deal was contingent on FERC’s authorization for MVP to commence service.
Notably, EQT still owned Equitrans when MVP began construction in 2018.
Crews said Appalachian Basin E&Ps would probably wait to ramp up their production for the new takeaway capacity.
“Everyone's looking at the forward curve thinking that 2024 is probably a wash,” Crews said. “Once you ramp up to increase production, it's probably a year to two years before that production gets online. So, most of our member companies are looking at 2025 as opposed to this year.”
Recommended Reading
Liberty Capitalizes on Frac Tech Expertise to Navigate Soft Market
2024-10-18 - Liberty Energy capitalized on its “competitive edge” when navigating a challenging demand environment in third-quarter 2024, CEO Chris Wright said in the company’s quarterly earnings call.
STRYDE Awarded Seismic Supply Contracts in Mexico
2024-09-03 - STRYDE was awarded two seismic node supply contracts in Mexico, the company’s first projects in the country.
Transocean Contracted for Ultra-deepwater Drillship Offshore India
2024-09-04 - Transocean’s $123 million deepwater drillship will begin operations in the second quarter of 2026.
Salunda, Intellilift Enter Pact to Optimize Automation in Well Construction
2024-08-21 - The agreement was signed following a successful pilot trial integrating Intellilift’s digital technologies with Salunda’s patented camera and wearable red zone monitoring solutions on a drilling rig.
Artificial Lift Meets Artificial Intelligence, with Hit and Miss Results
2024-08-23 - Oxy and Chevron are among companies trying to find the sweet spot between data analytics and machine learning with human intervention to optimize production and predict failures before they happen.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.