In the first part of the 1990s, cased-hole gravel pack was the primary sand control measure in Statoil; however, during the last decade openhole solutions have been taking over. Statoil has had good success with openhole gravel pack operations in horizontal wells up to 3,937 ft (1,200 m) in length. More recently, this sand control technique has been successfully combined with intelligent completions in wells on the Norne Satellite field.
Full-scale tests of the Statoil completion designs were conducted, for the most part, at Halliburton's service center in Stavanger. (All graphics courtesy of Halliburton) |
New completion design
This type of completion was particularly challenging. Reservoir-based completion tubular design sized the flow capacity of the inner isolation string to accommodate the reservoirs’ flow capability. The outside diameter of the intelligent completion assembly required use of a 7-in. screen base pipe to allow sufficient clearance space. Well casing design best practices held the production liner diameter to 9 5/8 in. to optimize the casing design and economics. The openhole completion lateral was reamed to a 9 1/4-in. diameter to allow both good gravel filter thickness around the 7-in. screens and good sealing of the swellable openhole packers. These requirements resulted in an unusually narrow clearance of only a half-inch between the installed packers and the inside diameter of the open hole. This meant that the gravel and carrier fluid would have to pass through this narrow space at several points in the well bore — and flow for up to 3,937 ft without bridging. Statoil wanted to develop a procedure that would ensure the integrity of the entire completion. The solution would have to be absolutely reliable for these subsea wells. To achieve this end, Statoil turned to full-scale testing.
New lightweight gravel developed by Hexion helped enable Statoil to successfully install a multizone completion in which the gravel had to be transported through multiple 1/2-in. annulus sections over the 3,116-ft (950-m) well bore. |
Statoil contracted to build and operate two full-scale models at the Halliburton service center in
The testing revealed an unanticipated issue. Since gravel packing in 8 1⁄2-in. open hole, 5 1/2-in. screens and 4-in. wash pipe on Heidrun had successfully been done both with and without 7.9-in. outside diameter (OD) swellable packers, it was assumed that the gravel would pass the 8 1/4-in. OD packers in a 4 1/4-in. inside diameter (ID) hole on Norne Satellite. Surprisingly, new testing which included the 8 1/4-in. swellable packer on the blank pipe showed that the gravel packed off around the packer. The pump rate could not be increased due to surface limitations.
Further testing showed that by increasing the OD of the wash pipe, the velocity outside the screens can be increased, keeping the rate constant. A successful test with 5 1/2-in. OD wash pipe confirmed that the gravel passed the critical area between the 9.4-in. ID open hole in the model and 8 1/4-in. OD swellable packer. But, due to long delivery time of 5 1/2-in. OD wash pipe, the team decided to perform testing with light weight gravel.
Successful packing was finally achieved with a new lightweight gravel developed by Hexion’s Oilfield Technology Group. The result was copied in wells, G-1H and J-2H, where 3,116 ft and 984 ft (950 m and 300 m), respectively, 9.25-in. openhole/7-in. screen annulus containing two 8 1/4-in. OD swellable packers were fully packed.
The ability to install this type completion provided Statoil with excellent abilities to proactively manage the reservoir. Selective, dependable isolation of the zones required, of course, sealing both the OD and ID
Low density, lightweight gravel provides buoyancy enhanced transport, lower pump rates, reduced friction pressure and long lateral packing involving close radial clearances. |
On another front, the service life of the completion assembly and the productivity of the well would have been severely reduced if a complete pack could not have been achieved. The new low density, lightweight gravel from Hexion proved to be key in this success.
The swellable isolation system is a packer based on the swelling properties of rubber in hydrocarbon. The system will swell to expand and seal the annulus around the pipe either in an openhole or cased-hole application. The system provides a single one-trip solution for effective zonal isolation in the well completion process. It has no moving parts and requires no down hole or surface activation. The system is used frequently in applications involving multilaterals, intelligent completions, screen completions, gravel-packs, stimulation treatments, etc. Of particular benefit to Statoil in this completion was the improved reliability by simplification of the overall process, the ability to effectively seal in open hole and reduced formation damage.
The new lightweight gravel is a resin-reinforced composite particle developed for use in sand control applications where lighter particle densities improve proppant placement and packing efficiency.For use in vertical, horizontal, deviated and “S” shaped well bores, the gravel has considerably lower specific gravity than sands or ceramics. Lower specific gravity provides reduced hydrostatics and allows completion fluids to transport particles farther into the well bore. This reduces treating pressures (surface/downhole) and hydraulic horsepower requirements.
Due to its lighter density, the new gravel has 38% greater volume, pound for pound, than sand or lightweight ceramics, It is appropriate for several deepwater applications:
• Gravel pack completions where pressure constraints keep velocities down and settling becomes an issue; and
• Long deviated/horizontal wells where transport to the toe is an issue (for example, completions with large screens or swellable system).
Recommended Reading
Range Resources Holds Production Steady in 1Q 2024
2024-04-24 - NGLs are providing a boost for Range Resources as the company waits for natural gas demand to rebound.
Hess Midstream Increases Class A Distribution
2024-04-24 - Hess Midstream has increased its quarterly distribution per Class A share by approximately 45% since the first quarter of 2021.
Baker Hughes Awarded Saudi Pipeline Technology Contract
2024-04-23 - Baker Hughes will supply centrifugal compressors for Saudi Arabia’s new pipeline system, which aims to increase gas distribution across the kingdom and reduce carbon emissions
PrairieSky Adds $6.4MM in Mannville Royalty Interests, Reduces Debt
2024-04-23 - PrairieSky Royalty said the acquisition was funded with excess earnings from the CA$83 million (US$60.75 million) generated from operations.
Equitrans Midstream Announces Quarterly Dividends
2024-04-23 - Equitrans' dividends will be paid on May 15 to all applicable ETRN shareholders of record at the close of business on May 7.