Nine liquefaction projects under construction in North America, with an ability to add capacity of 98.6 million tonnes per annum (mtpa), are expected to come online by the end of 2027, according to an analysis by Poten & Partners.
North American’s LNG capacity is currently about 86.6 mtpa, based on U.S. Energy Information Administration data. The additions tracked by Poten would more than double LNG export capacity.
Of the projects, six are located in the U.S., two in Canada and one in Mexico, Poten said in a Sept. 26 analysis.
In 2024, two projects will come online by year-end: Venture Global LNG’s 13.3 mtpa Plaquemines LNG Phase 1 (Louisiana); and Cheniere Energy’s 10 mtpa Corpus Christi Stage III (Texas).
In 2025, three projects will come online:
- QatarEnergy and Exxon Mobil’s 18.1 mtpa Golden Pass LNG (Texas);
- Shell, Petronas, PetroChina, Mitsubishi and Korea Gas’ 14 mtpa LNG Canada (British Columbia); and Venture Global’s 6.7 mtpa Plaquemines LNG Phase 2 (Louisiana) in mid-2025.
RELATED
Exclusive Q&A: LNG Canada to Open Country Up to Asian, Global Markets
In 2026, one project will come online: Sempra’s 3.3 mtpa Energia Costa Azul (Mexico), according to Sempra’s new timetable.
In 2027, three projects will come online:
- NextDecade’s 17.6 mtpa Rio Grande LNG Phase 1 (Texas) in early-2027);
- Sempra’s 13.5 mtpa Port Arthur LNG Phase 1; and
- Pacific Energy and Enbridge’s 2.1 mtpa Woodfibre LNG (British Columbia).
Poten expects LNG supply growth of around 186 mtpa over the next 10 years, which would represent a 3.8% CAGR. Also within the next 10 years, Poten expects the market share of the top 10 LNG producers to rise to 88% from around 82% now. Five of the top 10 producers are state controlled or state monopolies, according to Poten.
The U.S.’ share of the LNG market is expected to reach 29% in 10 years from 21% now, Poten said.
RELATED
No End in Sight: Biden’s Pause Has Far-reaching Consequences
Recommended Reading
DNO Makes Another Norwegian North Sea Discovery
2024-12-17 - DNO ASA estimated gross recoverable resources in the range of 2 million to 13 million barrels of oil equivalent at its discovery on the Ringand prospect in the North Sea.
Baker Hughes: US Drillers Keep Oil, NatGas Rigs Unchanged for Second Week
2024-12-20 - U.S. energy firms this week kept the number of oil and natural gas rigs unchanged for the second week in a row.
First Helium Plans Drilling of Two Oil Targets in Alberta
2024-11-29 - First Helium Inc. has identified 10 other sites in the Leduc formation.
US Drillers Cut Oil, Gas Rigs for First Time in Six Weeks
2025-01-10 - The oil and gas rig count fell by five to 584 in the week to Jan. 10, the lowest since November.
Huddleston: Haynesville E&P Aethon Ready for LNG, AI and Even an IPO
2025-01-22 - Gordon Huddleston, president and partner of Aethon Energy, talks about well costs in the western Haynesville, prepping for LNG and AI power demand and the company’s readiness for an IPO— if the conditions are right.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.