Canada is the world’s fifth largest oil producer. This is due in large part to the country’s vast reserves in and around Alberta, which contains the third-largest known oil reserves in the world.
Calgary-based ARC Resources Ltd. has called this oilrich region home for more than 20 years. The company has assets distributed across western Canada and operations that include E&P and development of conventional oil and natural gas.
Just across Alberta’s western border in northeast British Columbia, ARC Resources is one of the largest operators in the Montney region, which is considered one of the best tight gas plays in North America. And it was here that ARC Resources recently decided to begin optimizing the control systems it was using for its large multiwell natural gas production sites. The existing systems in place at these sites didn’t support artificial lift, which would soon be needed to maintain production levels. The systems also presented both expansion and safety challenges that the company wanted to address.
Operations at a crossroad
ARC Resources already had optimization programs at its smaller pads that contained only one to four wells. Control systems in place at these pads supported the use of artificial lift systems to help maintain or increase production as these wells depleted.
Larger pads of five or more wells, however, lacked control systems to support artificial lift systems. As some of these sites approached production milestones of 10 to 15 years, the company knew that it would need to make improvements in the near future.
“We were very successful with using assisted lift to keep production stable in the smaller fields,” said Charlie Kettner, programming specialist for ARC Resources. “We didn’t have the same optimization option in our bigger pads. So our production engineers wanted to find a control solution that would allow us to bring artificial lift to these fields as well.”
The existing controllers were not capable of handling the large amount of integrated operations required to run the entire well pad. As a result, the company had to use multiple controllers hardwired together along with remote terminal units (RTUs). This approach not only made the control infrastructure more complex and thus more prone to mistakes but also limited the amount of information available for control and monitoring.
The use of multiple hardwired controllers also presented safety challenges. ARC Resources relies on its control architecture to monitor toxic and explosive gases and to take actions such as turning on an exhaust fan or blocking wells as conditions dictate. But the controllers could lock up and freeze their outputs and give no indication that there was a fault. This forced the company to add “watch dog” timer hardware to monitor for such conditions.
A ‘canned package’
Kettner reached out to Rockwell Automation to begin discussions about optimization options that would support artificial lift systems at the large multiwell pads as well as simplify control and address safety concerns.
Their talks led them to the ConnectedProduction well manager system from Rockwell Automation, which includes an out-of-the-box Allen-Bradley ControlLogix programmable automation controller (PAC) and FactoryTalk View human-machine interface that requires no custom coding. The PAC gives ARC Resources single-platform control for large sites with up to 32 artificial lift wells and contextualized production information to help operators maintain optimal production levels and troubleshoot issues.
“It’s a canned package,” Kettner said. “You order it, install it and plug in your data to the points it’s looking for, and away you go.”
Kettner and his team decided to pilot the new technology at an eight-well production site named Sunrise near the town of Dawson Creek, British Columbia, before installing it at four other multiwell pad sites.
One of the benefits they first discovered during this trial run was the add-on instructions included in the ConnectedProduction, which helped them save about two days of programming during the installation process. Because the technology uses an open architecture, integration with other vendor hardware at the site was easy.
Enhanced visibility and safety
ConnectedProduction has eliminated the need for multiple controllers and RTUs that were previously in place at the Sunrise site. Now all well pad controls have been consolidated into a single control platform. In addition to simplifying the architecture, this will help lower hardware and software costs for the site.
The system also enables the use of artificial lift systems, including on/off timers and plunger lift systems, and provides visibility into those systems.
“Operators can track events in the Connected- Production solution to see what stage we’re in of the optimization cycle and make better decisions about what to do next,” Kettner said. “Operators can see, for example, that a timer well is not producing anymore and move to the next step of putting a plunger in the hole.”
The new system also is helping ARC Resources enhance safety by reducing the risk of faults going undetected at the Sunrise site.
“Now if something goes wrong with the processor, or if an I/O [input/output] rack comes undone, the ControlLogix platform can fault to a safe state where it shuts down all the processes,” Kettner said. “It takes all the power off the solenoids and essentially results in an emergency shutdown.”
Another benefit of the ConnectedProduction system is that it can support a flow-measurement card within the control panel. This has allowed Kettner to eliminate the use of a separate flow-measurement computer, which is saving his company tens of thousands of dollars at the site.
“We just plug the card into the rack, and it communicates on the backplane,” Kettner said. “It’s given us huge cost savings.”
Looking ahead, Kettner already has orders in to bring the ConnectedProduction system to at least four more large multiwell pads in the area.
“We’ve seen the value of the Rockwell Automation solution and want to bring it to our other sites where we need assisted lift,” he said. “On new pads we’ll implement this right from day one so it’s there and available when it’s needed. And we can just turn it on.”
Recommended Reading
Marketed: Hess 3-Well Package in Bakken Shale
2024-12-11 - Hess Corp. has retained EnergyNet for the sale of a three-well Bakken Shale package in Mountrail and Ward counties, North Dakota.
TotalEnergies Plans 300 MW Renewable Projects in Oman
2024-12-11 - Wind and solar power will be supplied to Petroleum Development Oman, aligning with TotalEnergies' multi-energy strategy in the country.
Exclusive Occidental, CrownRock Merge Into Team of Overachievers
2024-12-10 - Thaimar Ramirez, president and general manager for Occidental Petroleum’s Midland Basin Business Unit, said 100 days after closing the CrownRock acquisition production guidance keeps going higher.
TotalEnergies Closes $1.4B Acquisition of Malaysia’s SapuraOMV
2024-12-10 - TotalEnergies acquired SapuraOMV’s main assets in blocks SK408 and SK310, both located offshore Sarawak in Malaysia.
In Busy Minerals M&A Year, Freehold Grabs $152MM Midland Interests
2024-12-10 - Canadian player Freehold Royalties is getting deeper in the Permian with a CA$216 million (US$152 million) Midland Basin acquisition as minerals buyers intensify M&A in the basin.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.