Tulsa-based Intensity Infrastructure Partners launched an open season Feb. 3 to determine support for a natural gas transport line in the Bakken Shale, a basin with a growing need for natural gas egress. (Source: Shutterstock)
Tulsa-based Intensity Infrastructure Partners launched an open season Feb. 3 for a natural gas transport line in the Bakken Shale, a basin with a growing need for natural gas egress.
If built, the Intensity Pipeline will be a 126-mile, 42-inch diameter line with a 1.5 Bcf/d capacity. The intrastate route would take natural gas from production zones in western North Dakota to its terminating point in southern McLean County.

The open season ends at 1 p.m. CST on March 7. In its press release, Intensity announced its intention to “facilitate transparent and meaningful consultation with all stakeholders (landowners, community leaders, government agencies and potential customers).”
EIV Capital backs the company.
Production growth in the Bakken stressing the region’s energy supply has long been noticed by analysts. In May 2024, East Daley Analytics published a report titled “Gas Constraints May Limit Bakken Production Growth.”
The Bakken is a miniature version of the Permian Basin, an oil-focused production area producing an increasing amount of NGL-rich natural gas as it matures.
East Daley’s Bakken forecast “indicates gas demand is not increasing within the basin, leaving producers beholden to new pipeline expansions to move supply growth.” Natural gas production in the basin averaged just under 3.6 Bcf/d in 2023 and 2024, according to the U.S. Energy Information Administration.
If built, the Intensity line could follow another pipeline project in the region. The Federal Energy Regulatory Commission (FERC) approved permits for a natural gas project by two midstream players, TC Energy and Kinder Morgan, in October 2024.
TC Energy and Kinder Morgan’s Wyoming Interstate Co. (WIC) have planned a pipeline network project that would connect the Bakken with the Cheyenne hub in the Denver-Julesburg Basin. The project would add 430 MMcf/d of natural gas egress from the Bakken and is expected to be in service by the spring of 2026, according to the FERC application.
Recommended Reading
EOG Secures Award to Explore Abu Dhabi for Unconventional Oil
2025-05-16 - U.S. shale giant EOG Resources will evaluate 900,000 acres in a hydrocarbon-rich basin in Abu Dhabi under a new concession agreement with ADNOC.
E&P Highlights: April 28, 2025
2025-04-28 - Here’s a roundup of the latest E&P headlines, including field redevelopment in Iraq and an estimate of gas resources in Namibia.
NextEra: US Power Demand Will Call for Extra 71 Bcf/d Equivalent
2025-04-29 - NextEra Energy expects that of the total 450 GW of new electricity demand in the coming few years, 75 GW will be gas-fired—or some 12 Bcf/d. But turbines and skilled labor are needed.
Kongsberg Maritime to Equip New Construction Vessels for Sea1 Offshore
2025-06-04 - Kongsberg Maritime and Sea1 Offshore will also collaborate on a study to measure emissions reductions.
Wyoming Governor: Bet on Powder River Oil to Beat Market Challenges
2025-06-12 - Wyoming’s Powder River Basin has taken a quieter role in recent years as oil producers focused on the Permian. But state leaders remain confident, betting on a rebound in oil production from the once-promising shale play, Gov. Mark Gordon said in an exclusive interview.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.