Golden Pass LNG, a project delayed after the bankruptcy of its lead contractor in 2024, is closing in on an October commissioning date. (Source: Golden Pass LNG)
Golden Pass LNG, a project delayed after the bankruptcy of its lead contractor in 2024, is closing in on an October commissioning date, an application filed with the U.S. Department of Energy showed.
In a June 26 letter, executives for the joint venture project, Exxon Mobil and QatarEnergy, filed to re-export LNG that the facility plans to import for start-up operations beginning Oct. 1.
“This process is used to cool down the facility, generally the last step before starting to export,” said Zack Van Everen, an analyst at Piper Sandler, in a report on the filing.
According to the request, Golden Pass LNG seeks to sell up to 50 Bcf of natural gas in short-term export deals.
In the document, Golden Pass said it expected Oct. 1 to also be the first day for Train 1 to commence start-up operations. It could take several months for start-up operations to switch to production, followed by a ramp-up.
“This is a good indication that the first train will be up and running in 2026,” Van Everen said. “We model the second train starting to ramp mid-2026, with the last train ramping at the beginning of 2027.”
The document was filed with the Department of Energy, which oversees the export permits for U.S. LNG facilities. The project has already obtained its non-Free Trade agreement permit, which allows it to sell to countries that don’t have a trade deal with the U.S. The permits are crucial for LNG facilities, as the product is sold and traded globally.
Golden Pass’ nameplate capacity will run at about 18 million tonnes a year in Sabine Pass, Texas. The plant would be the ninth LNG export terminal in the U.S., if it starts on schedule.
In May 2024, the project hit a roadblock when its primary contractor, Zachry Group, declared bankruptcy. The parties eventually settled, but the project was pushed back from its original start date in 2024.
Recommended Reading
EnerMech Secures Offshore Decommissioning Contract with Exxon
2025-06-16 - The decommissioning of the Hoover and Diana fields south of Galveston, Texas is a first for EnerMech in the region.
Subsea 7 Wins Contract Award for Project Offshore Norway
2025-06-18 - The pipeline bundles Subsea7 will use for the project offshore Norway will be made in Scotland and deployed through 2027.
Subsea 7 Wins Service Contract Offshore West Africa
2025-05-21 - Subsea 7 will transport and install flexible pipelines, umbilicals and associated subsea components for the connection of a floating production, storage and offloading vessel.
E&P Highlights: May 27, 2025
2025-05-27 - Here’s a roundup of the latest E&P headlines, including new production offshore Brazil and new mapping for three U.S. basins.
Chevron Sees Tech Improvements Expanding its Portfolio
2025-04-29 - Chevron Corp.’s startup at Ballymore, offshore Louisiana, was its third major project to come online in the past year.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.