U.S. natural gas that’s stranded is more than likely going to stay that way, with some projects literally requiring an act of Congress (see the Mountain Valley Pipeline) to move new projects forward.
Speaking during the “Un-Stranding U.S. NatGas” session at Hart Energy’s America’s Natural Gas conference on Sept. 27, Justin Carlson, co-founder and chief commercial officer at East Daley Analytics, said demand growth of 17.4 Bcf/d is expected between 2023 and 2030.
“LNG will represent over 20% of U.S. demand, and that's a huge, obviously, shift from where we have been,” Carlson said.
Both supply and infrastructure are needed to meet that demand, and the growth period will likely be volatile, he said.
It’s “something that our market is going to have to monitor really, really closely,” Carlson said.
The 17.4 Bcf of growth will come from 14 LNG projects, over half of which have received final investment decision (FID). The question is whether gas supply will be able to meet the demand generated by new LNG projects in different regions. In some cases, gas supply exists but hasn’t received FID because there is no destination for production.
Production growth “effectively is stranded until we get new projects,” he said.
Once LNG projects reach FID, Carlson said he expects gas production projects to get approval to move forward.
Pipeline detective
Thomas Sharp, director of permitting intelligence for Arbo, also sees LNG driving demand for natural gas in the U.S.
But additional takeaway capacity coming is subject to regulatory risks, particularly if a pipeline must cross state lines and triggers Federal Energy Regulatory Commission (FERC) interest, or if it is a new pipeline, he said.
“These things play into the risk that any pipeline developer faces when they're trying to figure out how to move gas towards the demand center,” he said.
Pipeline projects to provide new capacity include: the LEAP Gathering Lateral Pipeline serving the Haynesville, which came online early; Whistler, which is now online in Texas; the Permian Highway, expected onstream by year-end; and Matterhorn, which is expected onstream in the third quarter of 2024, serving Texas.
Determining the status of intrastate pipelines in Texas and Louisiana is no easy task, Sharp said. With no FERC-like agency, no central repository of regulatory data is available.
“We have to be detectives. We have to figure out what's actually happening because you have disaggregated data across different states reporting different things,” he said.
Tracking activities like hydrostatic testing, clean air permits and land acquisition reveal clues about the status and location of projects, he said.
Regulatory issues can complicate pipeline projects, particularly those that cross state lines.
“They face obviously even more risk,” Sharp said. “We know that it took an act of Congress to get the MVP project to go through. So what does that mean for us? Essentially these greenfield [pipelines] are just extremely hard to build.”
Litigation is also used as a delaying tactic to keep pipelines from being built, and now the same strategies are being used to oppose renewable energy projects such as offshore wind farms, Sharp said.
“What all this adds up to is a lot of headwinds for interstate pipelines,” he said.
Recommended Reading
Kimmeridge’s Dell: Every US Basin Contains Both High-quality Inventory, Risk
2024-10-05 - Inventory management is a problem for the E&P space, no matter the basin, said Kimmeridge Energy Management's Ben Dell at Hart Energy's Energy Capital Conference in Dallas.
US Drillers Cut Oil, Gas Rigs for Third Week in a Row
2024-10-04 - The oil and gas rig count fell by two to 585 in the week to Oct. 4.
With Montney Production Set to Grow, US E&Ps Seize Opportunities
2024-10-02 - Canada’s Montney Shale play has already attracted U.S. companies Ovintiv, Murphy and ConocoPhillips while others, including private equity firms, continue to weigh their options.
Darbonne: The Geologic, the Man-made and the Political of Uinta Basin Outcrops
2024-10-01 - The oily western Uinta features layers of sedimentary deposits on view for visitors, mostly uninterrupted by man-made features but having an unseen pall of federal interference.
APA, TotalEnergies Aim for 'New Dawn' in Suriname with Massive GranMorgu Project
2024-10-01 - APA Corp. and TotalEnergies announced a $10.5 billion final investment decision for the GranMorgu project located offshore Suriname in Block 58. First production to come from a 220,000 bbl/d FPSO is slated to flow in 2028.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.