U.S. LNG company Freeport LNG has asked federal regulators to extend the amount of time it has to construct a fourth liquefaction train at its export plant in Texas until August 2028.
The U.S. Federal Energy Regulatory Commission (FERC) approved construction of the fourth train in May 2019, requiring Freeport to finish the train by May 2023, the company said in a filing on Monday.
In September 2020, FERC extended the time Freeport had to build the fourth train until May 2026.
Freeport, however, said it has not started to build Train 4 "due in large part to delays" stemming from the COVID-19 pandemic.
"The impact of the pandemic on the global community has now waned substantially, and global demand for U.S. LNG has rebounded and is projected to remain strong," Freeport said.
The company said it is "actively marketing Train 4 Project capacity to a number of potential off-takers, particularly in European markets, and is in active negotiations with several potential customers."
Freeport also said it is participating in the U.S.-European Commission energy security task force recently announced by U.S. President Joe Biden to assist in getting LNG supplies into Europe.
The United States has committed to supply LNG to Europe to help Washington's allies lessen their reliance on Russian energy following Moscow's invasion of Ukraine.
But since it would take about 48 to 56 months to build Train 4, Freeport said "it is not possible" to meet the current May 2026 in-service deadline.
The three operating trains at Freeport can turn about 2.1 billion cubic feet per day of natural gas into LNG.
Recommended Reading
Halliburton’s Low-key M&A Strategy Remains Unchanged
2024-04-23 - Halliburton CEO Jeff Miller says expected organic growth generates more shareholder value than following consolidation trends, such as chief rival SLB’s plans to buy ChampionX.
Deepwater Roundup 2024: Americas
2024-04-23 - The final part of Hart Energy E&P’s Deepwater Roundup focuses on projects coming online in the Americas from 2023 until the end of the decade.
Ohio Utica’s Ascent Resources Credit Rep Rises on Production, Cash Flow
2024-04-23 - Ascent Resources received a positive outlook from Fitch Ratings as the company has grown into Ohio’s No. 1 gas and No. 2 Utica oil producer, according to state data.
E&P Highlights: April 22, 2024
2024-04-22 - Here’s a roundup of the latest E&P headlines, including a standardization MoU and new contract awards.
Technip Energies Wins Marsa LNG Contract
2024-04-22 - Technip Energies contract, which will will cover the EPC of a natural gas liquefaction train for TotalEnergies, is valued between $532 million and $1.1 billion.