U.S. energy regulators extended to August 2028 the time U.S. LNG company Freeport LNG has to complete the fourth liquefaction train at its Texas export plant.
The three existing liquefaction trains at Freeport have been shut since June 8 after a pipe explosion. The company expects the plant to return to at least partial service in November.
The U.S. Federal Energy Regulatory Commission (FERC) said in a filing on Oct. 13 that Freeport has not yet started construction of the fourth train.
Freeport said the project was delayed by the replacement of its engineering, procurement and construction contractor and the COVID-19 pandemic, including the pandemic’s effects on the global supply chain and the impact on global LNG demand.
However, Freeport said demand for LNG has rebounded and it has been actively negotiating with potential off-take customers.
Natural gas prices in Europe are up about 111% this year as LNG demand soars after supply disruptions and sanctions linked to Russia's Feb. 24 invasion of Ukraine.
Freeport said it will take about 48 to 56 months to build the new fourth train, which made it impossible to meet the previous FERC deadline of May 2026.
FERC first approved construction of the fourth train in May 2019, requiring Freeport to finish it by May 2023.
In September 2020, FERC extended the deadline to May 2026.
The three trains already at Freeport can turn about 2.1 Bcf/d of natural gas into LNG.
Freeport's customers include units of Osaka Gas Co, JERA, BP, TotalEnergies and SK E&S. JERA is an alliance between units of Tokyo Electric Power Co Holdings Inc and Chubu Electric Power Co Inc.
Recommended Reading
EOG Joins OGMP 2.0 For Improved Methane Emissions Reporting
2023-01-05 - Joining the Oil and Gas Methane Partnership 2.0 will leverage data to advance EOG Resources’ operations and emissions performance.
Baker Hughes Q4 Earnings Soar, But Miss Analyst Expectations
2023-01-24 - Baker Hughes earnings per share jump 46% over Q3, but analysts were disappointed they weren’t as high as they expected.
Baker Hughes to Provide Equipment for Petronas Carbon Capture Project
2023-01-03 - Petronas' Kasawari offshore project is expected to be the largest carbon capture and sequestration facility in the world.
Technip Energies Awarded Project Management Consultancy by Kuwait Oil Co.
2023-01-05 - Similar contracts represent €250 million to €500 million (US$263 million to US$526 million) in revenue, Technip Energies said.
Williams Deepwater GoM Expansions Add Significant Growth
2023-02-22 - Williams reported another year of record financial performance, and six key projects underway in the U.S. Gulf of Mexico will drive impressive EBITDA growth in coming years.