U.S. pipeline company Equitrans Midstream Corp. said on Nov. 2 the venture building the $6.2 billion Mountain Valley natural gas pipeline from West Virginia to Virginia still expects the project to enter service in the summer of 2022.
Mountain Valley is one of several U.S. pipelines delayed by regulatory and legal fights with environmental and local groups that found problems with federal permits issued during President Donald Trump's administration.
When Mountain Valley construction started in February 2018, Equitrans estimated the 303-mile (488-km), 2.0 billion cubic feet per day (Bcf/d) project would cost about $3.5 billion and enter service by late 2018.
Equitrans said in its third-quarter earnings release that it expects environmental regulators in West Virginia and Virginia to complete their water quality reviews by Nov. 29 and Dec. 31, respectively, allowing the project to stick with its targeted summer 2022 start date.
Those so called Section 401 water quality certifications cover about 300 water crossings.
Equitrans, which has a roughly 47.8% ownership interest in Mountain Valley and will operate the pipe, said it has funded about $2.4 billion of the project as of Sept. 30.
Based on Mountain Valleys' targeted in-service date, Equitrans said it expects to start construction of the 75-mile (121-km) Mountain Valley Southgate extension from Virginia to North Carolina in 2022, which will allow that project to enter service in the spring of 2023.
Southgate will cost about $450 million to $500 million and is backed by a 0.3 Bcf/d commitment from Dominion Energy Inc.'s North Carolina unit.
Equitrans, which owns 47.2% of Southgate and will operate the pipe, said it could be expanded to provide up to 0.9 Bcf/d of gas.
The Mountain Valley venture is owned by units of Equitrans, NextEra Energy Inc., Consolidated Edison Inc., AltaGas Ltd. and RGC Resources Inc.
Recommended Reading
CNX, Appalachia Peers Defer Completions as NatGas Prices Languish
2024-04-25 - Henry Hub blues: CNX Resources and other Appalachia producers are slashing production and deferring well completions as natural gas spot prices hover near record lows.
TPH: Lower 48 to Shed Rigs Through 3Q Before Gas Plays Rebound
2024-03-13 - TPH&Co. analysis shows the Permian Basin will lose rigs near term, but as activity in gassy plays ticks up later this year, the Permian may be headed towards muted activity into 2025.
Comstock Continues Wildcatting, Drops Two Legacy Haynesville Rigs
2024-02-15 - The operator is dropping two of five rigs in its legacy East Texas and northwestern Louisiana play and continuing two north of Houston.
Evolution Petroleum Sees Progress on SCOOP/STACK, Chaveroo Operations
2024-03-11 - Evolution expects to participate in future development blocks, holding in aggregate over 70 additional horizontal well locations.
Rystad: More Deepwater Wells to be Drilled in 2024
2024-02-29 - Upstream majors dive into deeper and frontier waters while exploration budgets for 2024 remain flat.