Chevron has commenced water injection operations at its deepwater Gulf of Mexico Jack/St. Malo and Tahiti facilities in an effort to boost oil and natural gas recovery, the company announced Sept. 3.
Chevron achieved first water injection at the St. Malo field, located 280 miles south of New Orleans in 7,000 ft of water. The project, which was Chevron’s first waterflood project in the deepwater Wilcox trend, was delivered under budget and included the addition of water injection facilities, two new production wells and two new injection wells. It is expected to add approximately 175 MMboe to the St. Malo field’s gross ultimate recovery.
At the Tahiti facility, located approximately 190 miles south of New Orleans in around 4,100 ft of water, Chevron started injecting water into its first deepwater Gulf producer-to-injector conversion wells. The project included installation of a new water injection manifold and 20,000 ft of flexible water injection flowline.
Bolstered by multiple development projects since the start of operations, Jack and St. Malo together have cumulatively reached almost 400 MMboe of gross production, while the Tahiti facility recently surpassed 500 MMboe of gross production.
Chevron is operator of the St. Malo field, holding a 51% working interest. MP Gulf of Mexico LLC owns a 25% stake, with Equinor holding 21.5 %. Exxon Mobil and Eni each own have a 1.25% stake in the field.
Chevron operates the Tahiti facility with a 58% working interest, with Equinor and TotalEnergies holding 25% and 17%, respectively.
Recommended Reading
Occidental’s Stratos DAC Project on Track for 2025 Startup
2024-08-12 - Occidental Petroleum’s direct air capture commercial-scale facility in Texas is designed to capture up to 500,000 metric tons of CO2 annually.
Oxy’s 1PointFive Lands Federal Funds for South Texas DAC Hub
2024-09-12 - DAC technologies can pull CO2 directly from the atmosphere anywhere, avoiding the need to be near the point of emissions.
Spiritus Files Permit Application for Wyoming DAC Project
2024-08-09 - Targeting first phase startup by 2026, Spiritus on Aug. 8 said the direct air capture project is designed to remove 2 million tonnes of CO2 annually from the atmosphere.
SLB, Aker Carbon Capture JV Awarded Carbon Removal Contract
2024-08-01 - SLB and Aker Carbon Capture were awarded the front end engineering and design contract by CO280 Solutions for large-scale carbon capture plant at a pulp and paper mill.
Heirloom Makes Plans for Two DAC Facilities in Louisiana
2024-06-24 - Heirloom Carbon Technologies expects the facilities, located at the Port of Caddo-Bossier in northwest Louisiana, to remove about 17,000 tons of CO2 from the atmosphere starting in 2026.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.