
“As night follows day, an environmental challenge follows the approval of a natural gas pipeline,” a Court of Appeals, D.C. Circuit panel opinion said in ruling in favor of a Boardwalk Pipeline expansion project. (Source: Shutterstock.com)
A Federal Energy Regulatory Commission (FERC) permit issued for a natural gas pipeline in Indiana will stand after a federal appeals court dismissed a petition aimed at killing it.
On Jan. 7, a three-person panel for the Court of Appeals, D.C. Circuit, dismissed a petition against the FERC-issued permit for a 24-mile pipeline expansion by Boardwalk Pipelines that crosses the Kentucky-Indiana state line. An environmental group argued that the FERC should have analyzed non-gas alternatives before issuing the permit.
“As night follows day, an environmental challenge follows the approval of a natural gas pipeline,” wrote Judge Neomi Rao in the first sentence of the appellate court’s decision.
“Congress gave FERC authority to promote the development of interstate natural gas pipelines, but it left the choice of energy generation to the States,” Rao wrote.
In her opinion, Rao alluded to the many cases involving natural gas the D.C. Appeals Court has heard over the past few years. The D.C. court has primary jurisdiction over FERC decisions and therefore hears most of the petitions and lawsuits that follow permits over pipeline and LNG projects.
In 2024, the court issued rulings against permits for a Williams Cos.’ pipeline expansion project in the mid-Atlantic as well as two LNG production facilities in Texas.
In the Jan. 7 case, CenterPoint Energy proposed the pipeline as part of an overall energy transition project to retire a coal plant with wind and solar power. Houston-based CenterPoint also proposed a 460-megawatt gas-fired power station to serve as backup.
CenterPoint contracted Boardwalk Pipelines' Texas Gas Transmission line to supply the plant with a connection to an existing pipeline system in Kentucky. FERC approved the project, which crosses from Kentucky into Indiana where the plant is located, in 2023.
Citizens Action Coalition of Indiana, a group focusing on environmental policy and healthcare issues, filed a petition against the FERC permit. The D.C. appeals court heard the case in May 2024. The group argued that FERC’s analysis of the permit was inconsistent with the National Environmental Policy Act.
However, the court ruled that FERC appropriately kept its focus on the environmental impact of the proposed pipeline.
“FERC has no statutory authority to consider non-gas alternatives already rejected by the state,” Rao said in the ruling.

Recommended Reading
Energy Transfer, MidOcean Agree to Jointly Develop Lake Charles LNG
2025-04-09 - Under a non-binding heads of agreement with Energy Transfer, MidOcean Energy would fund 30% of Lake Charles LNG's project costs and be entitled to 30% of production—contingent on a final investment decision, the companies said.
Energy Transfer’s Lake Charles LNG to Supply Kyushu for 20 Years
2025-05-29 - Energy Transfer has agreed to supply Kyushu Electric Power Co. with up to 1 million tonnes per annum of LNG from its Lake Charles facility.
Golar’s FLNG Gimi Completes First Offload to British Sponsor
2025-04-17 - Golar LNG’s floating LNG vessel Gimi, located offshore Mauritania and Senegal, offloaded its first full cargo to LNG carrier British Sponsor.
Market Spoke, Hub Evolved: US NatGas Eyes International Prices
2025-05-22 - Global LNG pricing enters a new era as producers shift away from Henry Hub to international pricing benchmarks such as the Japan Korea Marker.
Texas Hits Record NatGas Production, Crude Holds Steady
2025-06-10 - The Texas Oil & Gas Association estimated that crude oil production in Texas held steady at 5.7 MMbbl/d, while NGL production also remained level at 4 MMbbl/d.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.