Work on the first of three subsea manifold installations for Aker BP’s Skarv Satellite Project (SSP) in the Norwegian Sea has begun, the operator announced Aug. 29.
Aker BP submitted to the Norwegian Ministry of Petroleum and Energy a Plan for Development and Operation (PDO) for the SSP development along with two other projects in December 2022, and the project was approved in June. The SSP will extend the lifetime for the Skarv FPSO, which began production in 2013, to about 2040.
The NOK 17 billion ($1.7 billion) SSP is the largest development in the Norwegian Sea in recent years, and comprises the Alve Nord, Idun Nord and Ørn gas and condensate discoveries. Recoverable resources in the three developments are around 120 MMboe, mainly gas. Production start is planned for the third quarter of 2027.
Each of the developments consists of a subsea template with four well slots and two wells to be tied back to the Skarv FPSO located in the northern part of the Norwegian Sea. Development of the three discoveries is being coordinated by a unified project team to reduce costs through shared infrastructure.
Aker BP is using the company’s alliance model in the implementation phase, including the Subsea Alliance with Aker Solutions and Subsea 7, and the Modification Alliance with Aker BP and Aker Solutions. The Modification Alliance will carry out comprehensive modifications on the Skarv FPSO so it can receive production from the satellite developments.
License partners in Alve Nord include operator Aker BP with 68.1%, Wintershall DEA with 20% and PGNiG with 11.9%. Partners in Idun Nord include operator Aker BP with 23.8%, Wintershall DEA with 40% and Equinor with 36.2%. Partners in Ørn include operator Aker BP with 30%, PGNiG with 40% and Equinor with 30%.
Recommended Reading
No Rush: Post-M&A Frenzy, Divestiture Market to Pick Up by 2025
2024-10-07 - Lenders with a variety of capital structures are poised to fund the upcoming portfolio rationalization in the post-consolidation era, bankers and deal advisers said at Hart Energy’s Energy Capital Conference.
Tellurian Stockholders Approve $900MM Woodside Acquisition
2024-10-07 - Woodside Energy has said it expects to close the acquisition of Tellurian, and its Driftwood LNG permitted facility, by December.
Murphy Oil Names New CEO, Adds Two Directors to Board
2024-10-06 - Murphy Oil’s current COO Eric M. Hambly has been appointed to CEO and president, succeeding Roger W. Jenkins. The board also added Hambly and Robert B. Tudor III as new directors.
Utica Oil E&P Infinity Natural Resources Latest to File for IPO
2024-10-05 - Utica Shale E&P Infinity Natural Resources has not yet set a price or disclosed the number of shares it intends to offer.
Private Equity Gears Up for Big Opportunities
2024-10-04 - The private equity sector is having a moment in the upstream space.
Comments
Add new comment
This conversation is moderated according to Hart Energy community rules. Please read the rules before joining the discussion. If you’re experiencing any technical problems, please contact our customer care team.